2.3.5 Lifting the base plate

Required equipment
Equipment
Lifting eye, M16
Lifting slings
Hole configuration
xx0200000096
A
Lifting, base plate
1
2
3
3HAC039838-001 Revision: C
Attachment holes for lifting eyes (x3)
Action
CAUTION
The base plate weighs 353 kg! All lifting equipment
used must be sized accordingly!
Fit lifting eyes in specified holes.
Fit lifting slings to the eyes and to the lifting device.