2 Installation and commissioning
2.3.3 Lifting robot with lifting slings
Continued
Equipment
Roundsling
Slings attached directly onto robot
This section details how to lift and move the robot using lifting slings when these
are attached directly onto the robot frame.
1
2
3
4
5
6
7
72
Art. no.
-
Action
Run the overhead crane to a position above
the robot.
Position the robot as detailed in enclosed in-
struction!
Note
If the robot is equipped with forklift pockets,
it is necessary to remove these in order to
reach the lower holes in the frame. These are
used to attach the hooks of the lifting slings.
Fit lifting device, robot to the robot as de-
scribed in enclosed instruction!
CAUTION
The IRB 760 robot weighs 2300 kg.
All lifting accessories used must be sized ac-
cordingly!
WARNING
Personnel must not, under any circumstances,
be present under the suspended load!
Raise overhead crane to lift the robot.
© Copyright 2013 ABB. All rights reserved.
Note
1 m, lifting capacity: 2,000 kg.
Used to secure against rotation.
Note
Art. no. is specified in
ment on page
71.
Release the brakes if required as de-
tailed in section
Manually releasing the
brakes on page
73.
Shown in the figure
Illustration, lifting
slings on page
71.
Art. no. is specified in
ment on page
71.
Make sure all hooks and attachments
maintain their correct positions while
lifting the robot!
Always move the robot at very low
speeds, making sure it does not tip.