User Manual for the NETGEAR 7300S Series Layer 3 Managed Switch Software
Moving a Master to a Different Unit in the Stack
Using the "movemanagement" command, move the master to the desired unit number. The
1.
operation may take between 30 seconds and 3 minutes depending on the stack size and
configuration. The command is movemanagement <fromunit-id> <tounit-id>
Make sure that you can log in on the console attached to the new master. Use the show switch
2.
command to verify that all units rejoined the stack.
It is recommended that the stack be reset with the reload command after moving the master.
3.
Removing a Master Unit from an Operating Stack
First, move the designated master to a different unit in the stack using
1.
Different Unit in the Stack" on page
Second, using
"Removing a Unit from the Stack" on page
2.
stack.
Merging Two Operational Stacks
It is strongly recommended that two functioning stacks (each having an independent master)
1.
not be merged simply by the reconnection of stack cables. That process may result in a number
of unpredictable results and should be avoided.
Always power off all units in one stack before connecting into another stack.
2.
Add the units as a group by unplugging one stacking cable in the operational stack and
3.
physically connecting all unpowered units at that point.
Completely cable the stacking connections, making sure the redundant link is also in place.
4.
Then, power up each unit, one at a time, by following
5.
on page
12-12.
12-14
12-14.
202-10088-01, March 2005
"Moving a Master to a
12-12, remove the unit from the
"Adding a Unit to an Operating Stack"