Section 6: Keithley Interactive Test Environment (KITE)
4.
Start execution. Click the green triangular Run Test/Plan toolbar button (see below), select
Run in the KITE Run menu, or press the F6 keyboard key.
Figure 6-195
KITE Run Test/Plan icon
The green Run Test/Plan toolbar button becomes gray, the Subsite Plan executes, and the
square Abort Test/Plan icon illuminates red for the duration of the test (see below).
Figure 6-196
KITE Abort Test/Plan button
NOTE
Simultaneously, the Execution Indicator (see below) traces miniature curves and changes
color for the duration of the Subsite Plan execution.
Figure 6-197
KITE Execution Indicator button
As each test in the Subsite Plan executes, the Test/Plan Indicator box displays the data
label for the test (refer to
label includes the test identity and the site number that you specified in the Site Navigator.
See the example below.
Figure 6-198
KITE Test/Plan indicator box
Subsite cycling
If a Subsite Plan is configured for subsite cycling, it will be repeated a specified number of times.
For example, if the subsite plan is configured to cycle two times, the Subsite Plan will run two
times. Test data is acquired for all cycles that are run. For details, see
section.
Subsite cycling is started by clicking the following Run Test/Plan and Cycle Subsites button:
Figure 6-199
KITE Run Test/Plan and Cycle Subsites button
Subsite cycling can be terminated at any time by clicking the red Abort Test/Plan button.
6-164
If you should need to abort the Subsite Plan execution, click the red Abort Test/Plan
toolbar button or press the PAUSE/BREAK keyboard key.
Test data file naming conventions later in this
Return to
Run Test/Plan and Cycle
Section Topics
Model 4200-SCS Reference Manual
section). The data
Subsite cycling later in this
4200-901-01 Rev. S / May 2017

Advertisement

Table of Contents
loading

Table of Contents