370 Chapter 8: Recovery/replacement procedures
Procedure 3: Hardware powerdown
Procedure 4: Power up the Application Module or IPE
Module
553-3211-510 Standard 1.0 October 1998
1
Complete Procedure 1: Software powerdown.
2
When the system confirms that it is secured for powering down, set
the MPDU circuit breaker for the Application Module to OFF (down)
or press the black power pushbutton on the IPE Module.
The top breaker powers the Application Module next to the MPDU
(on the left-hand side facing the AEM). The bottom breaker powers
the second module.
Wait 60 seconds before adding or removing hardware, or before
trying to restore power.
1
Set the MPDU circuit breaker for the Application Module to ON (up)
or press the power pushbutton on the IPE Module.
Reboot messages appear on the system console. If the CCR
application has been configured for auto-start, the application starts
up automatically.
2
If the CCR application does not have auto-start enabled, log in as
maint.
3
At the Òmaint>Ó prompt, type applstart and press [Return].
For more information on auto-start, refer to the Meridian
Link/Customer Controlled Routing Installation and Upgrade Guide
(NTP 553-3202-210).