Final Maintenance Procedure; Introduction - Nortel Meridian 1 Manual

Table of Contents

Advertisement

Final maintenance procedure

Introduction

Perform the final maintenance procedure (Procedure 4) to verify that the
Meridian 1 is operating properly and that there are no remaining faults.
Procedure 4
Final maintenance procedure
1
Make sure all cards that may have been removed are reinserted in
their assigned location and enabled.
2
Make sure all wiring and connectors that may have been disconnected
are reconnected.
3
Make sure all loops and shelves that should be enabled are enabled.
Note: Digital telephones on a network loop that was disabled may not
be restored when the loop is enabled. Each telephone should be
individually disabled and reenabled through LD 32. Service may also
be restored by disconnecting and reconnecting the telephone line
cord.
4
Make sure all circuit breakers are set to ON and any fuses (in power
panels or auxiliary equipment) are inserted.
Page 177 of 190
Meridian 1 Fault clearing

Advertisement