Commissioning
6.2.3
Start first commissioning of a synchronous motor
•
Switch on enable at STOA (X11.3) and STOB (X13.3).
•
Switch off enable at IN1D (X11.4) and IN2D (X11.5), if a circuit for control via control terminals is
installed.
Switch on the power supply.
•
Start commissioning (Setup) on operator panel.
•
If the unit is in "as-delivered" condition or after resetting the unit to the factory settings, the guided
commissioning procedure is started automatically. The operator panel displays the menu item "Setup".
Guided commissioning can also be opened by selecting the "Setup" menu.
Setup
Parameter
Start commissioning.
Using arrow keys, select:
− Complete commissioning or
− Measure motor data only.
− Commissioning of a communication interface
Refer to chapter "
Note
− Select "Full" setup if the frequency inverter is commissioned for
the first time.
− Select "Motor" setup if only the motor data are to be measured
and other settings are not to be changed.
Select data set 0.
Select another data set for commissioning of several motors or for
different operating points.
P30
Configuration (control method).
Using arrow keys, select:
− 110 - IM
− 410 - IM
− 610 - PMSM
1
For simple applications (e.g. fans, pumps). Control according to V/f-characteristic. In the case of control via
operator panel: Select "UF". IM: Induction machine (asynchronous motor).
2
Control of an induction machine (asynchronous motor). For higher demands on speed or torque accuracy. In
the case of control via operator panel: Select "Foc".
First commissioning
RUN
ESC
1
: sensor-less control(SLC) or
2
: sensor-less field-orientated control or
1
: sensor-less field-orientated control
65
STOP
ENT
06/2013
Operating Instructions
Display
ENT
or
ENT
ENT
ENT
or
or
Agile
Need help?
Do you have a question about the Agile and is the answer not in the manual?
Questions and answers