2. Start the engine.
3. Park the windrower on level ground.
4. Press header raise button (A) on the ground speed
lever (GSL) until the header reaches maximum height.
Continue to hold the header raise button for 3–4 seconds
to rephase the lift cylinders.
5. Lower the header to approximately 150 mm (6 in.) off the
ground.
6. Ensure that member (A) is against link (B).
7. Shut down the engine, and remove the key from
the ignition.
8. Measure the distance to the ground at both ends of the
header to determine if the header is level.
9. If adjustment is necessary, start the engine and resume the
float. For instructions, refer to
Float, page
240.
10. Lower the header onto the ground until member (A) lifts
away from link (B) on both sides of the machine.
11. Shut down the engine, and remove the key from
the ignition.
262171
OPERATION
Removing and Restoring
254
Figure 5.125: Ground Speed Lever (GSL)
A
B
Figure 5.126: Lift Linkage
A
B
Figure 5.127: Lift Linkage
A
Revision A