Searching For Nodes That Can Be Accessed; Example Of First Commissioning With Starter - Siemens Sinamics S110 Function Manual

Hide thumbs Also See for Sinamics S110:
Table of Contents

Advertisement

Commissioning with PROFIBUS

3.5 Example of first commissioning with STARTER

What to do?
4.
Summary
5.
Configure the drive
unit.
3.4.3

Searching for nodes that can be accessed

To search for a drive unit online, the drive unit and the PG/PC must be connected via
PROFIBUS. The interface must be set correctly in STARTER.
3.5
Example of first commissioning with STARTER
The example provided in this section explains all the configuration and parameter settings
that are required for first commissioning. Commissioning is carried out using the STARTER
commissioning tool.
Requirements for commissioning
1. The checklist for commissioning (Table 1-1 or 1-2 in Section 1.1) has been filled out and
2. STARTER is installed and activated.
3. The power supply (24 VDC) is switched on.
58
You have now created the project.
-> Click "Complete".
Once you have created the project, you have to configure the drive unit. An example appears
in the next section.
the points ticked off.
--> see the "Readme" file on the STARTER installation CD.
How to do it?
Function Manual, 10/2008, 6SL3097-4AB10-0BP0