Check list for commissioning blocksize power units
The following checklist must be carefully observed. The safety information in the Manuals
must be read and understood before starting work.
Table 2- 1
Are the ambient conditions in the permitted range (see Equipment Manual)?
Is the component firmly attached to the fixing points provided?
Can the cooling air flow unobstructed?
Have the ventilation clearances for the components been observed?
Are all necessary components of the configured drive line-up installed and available?
Have the DRIVE-CLiQ limitations for CU305 been observed?
Have the line-side and motor-side power cables been dimensioned and routed in
accordance with the ambient and routing conditions?
Have the maximum permissible cable lengths between the frequency converter and
the motor (depending on the type of cables used) been observed?
Have the cables been properly connected with the correct torque to the component
terminals?
Have the cables for the motor and low-voltage switchgear been connected with the
required torques?
Has all wiring work been successfully completed?
Are all connectors correctly plugged in and screwed in place?
Have all the screws been tightened to the specified torque?
Are the shield connections installed correctly?
Drive functions
Function Manual, 10/2008, 6SL3097-4AB10-0BP0
Check list for commissioning blocksize
Commissioning preparations for PROFIBUS
2.1 Requirements for commissioning
Check
O. K.