7. Install the counter shaft rear bearing outer race,
shim and retainer.
Installation Notice
Tightening Torque
Notice: Using a punch and hammer, bend the lock
tabs on the retainer.
YAD5B750
8. Install the following parts :
•
Install the main shaft into case.
•
Install the main shaft rear bearing outer race
into the rear of the case.
•
Install the 4th speed blocking ring onto the front
of the main shaft.
•
Install the input shaft onto the front of the main
shaft.
•
Install the input bearing retainer without shim
onto the front of the case.
•
Using a torque wrench, tighten the 4 bolts.
Installation Notice
YAD5B760
Tightening Torque
9. Install the 5th speed drive gear and blocking ring
on the counter shaft.
10. Install the 5th synchronizer and rail/fork.
11. Install the 5th synchronizer snap ring and oiling
funnel.
YAD5B770
20 N•m (15 lb-ft)
20 N•m (15 lb-ft)