Mode:
RAMPing:
Step:
Test Time:
Ramp:
Dwell:
Test:
Fall:
Twin Port
Page 32 of 177
www.valuetronics.com
The test which is to be performed such as AC Hipot (AC),
DC Hipot (DC), Insulation Resistance (IR), Leakage
Current (LC), Ground Bond (GB) or Open/Short Circuit
(OSC).
The gradual increase or decrease of voltage or current over
a period of time (step).
The Guardian 6100 Plus can perform up to 50 tests in a
sequence. The step number indicates in which order the
tests will be performed. For example if step 1 is a ground
bond test, step 2 an AC hipot and step 3 an insulation
resistance measurement then when a test is started the
G6100 Plus will perform a ground bond test followed by an
AC hipot then an insulation resistance measurement.
The period of time for the voltage to climb to the
programmed level.
The period of time for the voltage to settle at the
programmed level. (a.k.a.: delay)
The period of time that the voltage is applied to the DUT.
The period of time for the voltage to decrease back to 0.
TM
:
Exclusive feature of Guardian 6100 Plus. Twin Port
allows for optimum speed performance by combining the
Ground Bond test with the Hipot test (AC or DC) so that
they run at the same time.
150799 Rev A3
TM
Operation
Need help?