Continue with steps 22 -25 by attaching the dummy load box outlined in Table 4-5
between the High voltage output and the return.
Press [UP] to go to CAL step 22. (IRR 250V Range1 1GΩ)
Press [STOP]
Press [START]
Enter the value of the resistor standard followed by [ENTER]
Press [STOP]
Press [UP] to go to CAL step 23. (IRR 500V Range2 100MΩ)
Press [STOP]
Press [START]
Enter the value of the resistor standard followed by [ENTER]
Press [STOP]
Press [UP] to go to CAL step 24. (IRR 500V Range3 10MΩ)
Press [STOP]
Press [START]
Enter the value of the resistor standard followed by [ENTER]
Press [STOP]
Press [UP] to go to CAL step 25. (IRR 1000V Range4 10MΩ)
Press [STOP]
Press [START]
Enter the value of the resistor standard followed by [ENTER]
Press [STOP]
[DEVICE] Calibration is complete.
Press [EXIT]
Now to calibrate the Leakage Current scanner. Turn OFF the G6100 Plus instrument.
Remove the 6000-07 scanner and switch the [JMP1] switch on the rear of the 6000-07 PC
board to "CAL". This switch is hardware-protected so no calibration data will be lost.
Turn ON the G6100 instrument
In Main Menu, press [3] = CALIBRATION
Display prompts: "PASSWORD: ______"
Press [7][9][3][1] [ENTER]
Press [LC BOARD] to enter Leakage Current Calibration.
The Leakage Current (LC) calibration is divided into two parts – the meter calibration
and the power meter calibration.