Oracle EAGLE Installation Manual page 41

Table of Contents

Advertisement

Felt tip pen
Isolation sheet (template in mounting hardware kit) to mount one frame
Verify with a customer representative that the required area dimensions and equipment
1.
location corresponds to the marked floor plan.
Use the floor plan provided with the engineering site file specifications to mark the front
2.
base line and the borders of the first frame with the chalk line (refer to
Figure 4-7
Typical Floor Layout for Frames
Align the frame isolation sheet/template (refer to
3.
anchor location in the middle of each oval anchor slot and to mark the corners of the first
frame.
Create another chalk line that allows 6 inches between each frame for correct spacing.
Align the template again against the chalk line and continue the process of aligning,
marking, and moving the template until the site specific number of frame spaces have
been laid out on the floor.
Use the felt tip pen to mark the anchor location in the middle of each slot and corners for
4.
each successive frame.
Figure 4-8
Isolation Sheet/Template for Frame
The next section describes how to prepare a raised floor for frame installation.
Figure
Figure
4-8) along the chalk line to mark
Chapter 4
Floor Preparation
4-7).
4-7