The example test procedure that follows covers the testing of the Shark® 200 meter.
The test procedure used for the Standard shall be determined by the manufacturer of
the Standard used.

Test Procedure

1. All circuits and equipment must be de-energized.
2. Connect the three phase potential input lines to "Va", "Vb", and "Vc" and the neu-
tral to "V-Ref" & "GND."
3. Connect power leads to the "L" and "N" connections.
4. Monitor the #1 test pulse by placing the photo detector over the #1 LED.
5. Connect the three phase current inputs to the current terminals associated with the
test pulse LED being monitored. There must be no other current inputs connected.
6. Energize the Standard and the Shark® 200 meter. To assure accuracy, both must
be on for a minimum of 30 minutes.
7. Energize the sources and wait for the outputs to stabilize before starting the test.
8. Start the test as per the appropriate procedure for the Standard and/or comparator
used.
9. When the test is completed, de-energize the sources.
10. Place the photo detector over the next test pulse to be monitored.
11. Repeat steps 5 through 10 until all test pulses are checked.
12. De-energize all circuits and remove power from the Standard, sources, and the
Shark® 200 meter.
13. Disconnect all connections from the Shark® 200 meter.
Electro Industries/GaugeTech
Electro Industries/GaugeTech
The Leader In Power Monitoring and Smart Grid Solutions
The Leader In Power Monitoring and Smart Grid Solutions
6: Using the Shark® 200 Meter
#
Doc
E149701
6-19

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Shark 200t

Table of Contents