Creating a Perimeter Analysis Schedule
Use the following procedure to create a schedule for analyzing the perimeter of masses in a conceptual
design, based on the scenario described in
depending on the information that you want to show in the schedule.
To create a perimeter analysis schedule
1 Create mass floors.
2 Click View tab
3 In the New Schedule dialog, do the following:
4 On the Fields tab of the Schedule Properties dialog, for Scheduled fields (in order), add the
5 Click the Sorting/Grouping tab, and do the following:
6 Click the Formatting tab, and do the following:
608 | Chapter 12 Massing Studies
See
Creating Mass Floors
Create panel
a For Category, click Mass Floor.
If Mass Floor does not display by default, select Show categories from all disciplines.
b For Name, specify the schedule name.
c Select Schedule building components.
d Click OK.
following fields:
Mass: Type
Level
Floor Perimeter
a For Sort by, select the following:
Mass: Type
Ascending
Footer
Title and totals
Blank line
b For Then by, select both Level and Ascending.
c At the bottom of the dialog, select the following:
Grand totals
Title and totals
Itemize every instance
a Under Fields, select Floor Perimeter.
b For Alignment, select Right.
c Select Calculate totals.
Perimeter Analysis Example
on page 596.
Schedules drop-down
on page 607. Specific steps may vary
Schedule/Quantities.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 256B1-05A761-1301 - AutoCAD Revit Structure Suite 2010 and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents