Table 664:
Settings for configuration example 1
Setting name
Shot number CBB1
Init signals CBB1
First reclose time
Shot number CBB2
Init signals CBB2
Second reclose time
Example 2
There are two separate sequences implemented with three shots. Shot 1 is
implemented by CBB1 and it is initiated with the high stage of the overcurrent
protection (I>>). Shot 1 is set as a high-speed autoreclosing with a short time delay.
Shot 2 is implemented with CBB2 and meant to be the first shot of the autoreclose
sequence initiated by the low stage of the overcurrent protection (I>) and the low stage
of the non-directional earth-fault protection (Io>). It has the same reclosing time in
both situations. It is set as a high-speed autoreclosing for corresponding faults. The
third shot, which is the second shot in the autoreclose sequence initiated by I> or Io>,
is set as a delayed autoreclosing and executed after an unsuccessful high-speed
autoreclosing of a corresponding sequence.
A071272 V1 EN
Figure 345:
Autoreclosing sequence with two shots with different shot settings
according to initiation signal
Setting value
1
7 (lines 1, 2 and 3 = 1+2+4 = 7)
0.3s (an example)
2
7 (lines 1, 2 and 3 = 1+2+4 = 7)
15.0s (an example)