ABB RELION Series Technical Manual page 219

Grid automation
Hide thumbs Also See for RELION Series:
Table of Contents

Advertisement

1MRS758755 A
REC615 and RER615
Technical Manual
A070982 V1 EN
Figure 118:
Functionality of numerical multiple-stage overcurrent protection
The coordination plan is an effective tool to study the operation of time selective
operation characteristics. All the points mentioned earlier, required to define the
overcurrent protection parameters, can be expressed simultaneously in a coordination
plan. In
Figure
119, the coordination plan shows an example of operation
characteristics in the LV-side incoming feeder and radial outgoing feeder.
Section 4
Protection functions
213