Power down procedure

Some replaceable components require a power down as part of upgrade or
replacement procedures. This section describes how to power down the
replaceable components.
Notice:
Before powering down the failed components, ensure that a back up data
exists. If a back up of data does not exist or is old, perform the backup
procedure first.

Server Blade

There are three ways to power down a blade; listed in order of priority (A) to
(C).
Use one of the following procedures to power down the server blade.
(A) Use web console
This procedure initiates a remote shutdown of applications and OS before the
server blade becomes standby mode.
(A)-1 For CB 520A A1, CB 520H A1/B1/B2/B3/B4, CB 540A A1/B1,
Non-SMP CB 520X B1/B2/B3
1
Ensure that Power LED lights in green.
.
2
Logon to the web console and select Resource.
.
3
Select Modules > All Modules > Server blades > the failed server
.
blade.
4
Select Condition tab.
.
5
Click Power OFF.
.
4-58