Training 1: Setting The Gauge Manifold - Kubota KX080-3 Workshop Manual

Hide thumbs Also See for KX080-3:
Table of Contents

Advertisement

WSM KX080-3 Service

Training 1: Setting the gauge manifold

1) Close the gauge manifold s valves (for HI and LO).
2) Connect the charging hoses. (Connect the red one to HI and the blue one to LO.)
3) Slightly loosen the high-pressure and low-pressure valves to let air out of the hoses.
4) Fully close the high-pressure and low-pressure valves.
(1) LO Pressure Gauge
(2) HI Pressure Gauge
(3) LO Pressure Side Valve
(4) HI Pressure Side Valve
(5) Schrader Valve
(1) LO Pressure Side Valve
(2) HI Pressure Side Valve
(3) Blue Hose
(4) Green Hose
(5) Red Hose
VI-S-21
VI Air Conditioner

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents