26.2 Preparatory Procedures for Monitoring
The following shows the procedures to be taken before monitoring and corresponding reference sections.
Connect the GOT to the PLC.
Install the OS onto the GOT.
Make sure that the OS is installed on the GOT.
Set the communication interface. (Communication
settings)
Download the project data.
Attach the communication unit and connect the cable.
Make sure that the GOT recognizes the connected
equipment.
26 - 4
26.2 Preparatory Procedures for Monitoring
Refer to each chapter.
Section 26.2.1
Installing OS onto GOT
Section 26.2.2
Checking OS installation on GOT
Section 26.2.3
Setting communication interface
(Communication settings)
Section 26.2.4
Downloading project data
Section 26.2.5
Attaching communication unit and
connecting cable
Section 26.2.6
Verifying GOT recognizes connected
equipment