ACCEPTANCE TEST CHECKLIST FOR OPTI-6100
System Acceptance Checklist-Summary
System: _____________________________
Test Step
1. Verify Power Connection
2. Verify DS1 Wiring
3. Verify DS3 Wiring
4. Verify Timing Input Connections
5. Verify Fan Operation
6. Verify Alarm Relay Output Connections
7. Verify IP LAN Connection
1. Write N/A by any step which is not applicable to the installed configuration.
2. Fiber connections and Ethernet tributary connections are not addressed herein since they are terminated on the
modules and connected when those modules are installed.
Comments
Installation Engineer Sign-Off
Name (print): _______________________________ Date Completed: ____________________________
Signature: _______________________________
Customer Sign-off
Name (print): _______________________________ Date Completed: ____________________________
Signature: _______________________________
61184500L1-5L
Appendix A, Acceptance Test Procedure - Acceptance Test Checklist for OPTI-6100
Table A-1. Test Step Checklist
Completed (Initial)
A-13