FOLLOW-UP PROCEDURES

Once these procedures are complete, the OPTI-6100 chassis is ready for turnover.

Verify OPTI-6100 Chassis Wiring to the DSX-1

This procedure details the test steps which must be performed to verify that an OPTI-6100
chassis has been properly wired to the DSX-1 This procedure should be performed by two
people: one at the chassis under test and the other at the MDF.

Prerequisite Procedures

The following procedure must be completed prior to verifying the OPTI-6100 chassis wiring to
the DSX-1. If necessary, refer to the appropriate documentation before proceeding. The prereq-
uisite procedure is as follows:
OPTI-6100 Installation and Turn-Up Practice (P/N 61184500L1-5)

Tools and Materials Required

PC connected to the craft port or through Telnet

Procedure

1. Power on the DS1 test set and configure for a 2
2. Connect a DS1 cable from the Tx output of the test set to the Rx input of the MDF facility
#1 to be tested.
3. Connect a DS1 cable from the Rx input of the test set to the Tx output of the MDF facility
#1 to be tested.
4. Connect a serial cable to the craft port of the OPTI-6100.
5. Open a terminal session and configure the baud rate to 19200.
6. Login to the OPTI-6100 with a valid username and password. The default username is
ADMIN. The default password is PASSWORD.
7. After logging in, select
8. From the HS 1 menu, select
9. From the Provisioning Menu, select
10. From the Service States menu, select
11. From the Equipment Provisioned State menu, select
12. From the Service States menu, select
13. From the Facility Provisioned State menu, select
14. Press
one time to return to the
E
SC
15. From the Provisioning menu, select
16. From the STS1 Mapping menu, select the HS1 STS-1 to be mapped, and press
If there is no mapping, select HS1 STS-1 #1. Do not use menu options #4-15. Only use HS1
with the default payload type for this test.
61184500L1-5L
Appendix A, Acceptance Test Procedure - Follow-Up Procedures
from the Main menu, and press
HS 1
, and press
Provisioning
Service States
Equipment Provisioned State
Facility Provisioned State
Provisioning
STS-1 Mapping
23
-1 test pattern and B8ZS line coding.
.
E
NTER
.
E
NTER
, and press
.
E
NTER
, and press
(in service), and press
IS
, and press
(in service), and press
IS
menu.
, and press
.
E
NTER
.
E
NTER
.
E
NTER
.
E
NTER
.
E
NTER
.
E
NTER
A-3