60 Site planning and hardware deployment
Assess floor layout
The deployment procedure changes according to the similarities and
differences of the floors.
All floors have the same layout.
To begin a multi-floor deployment if all floors have the same layout,
deploy one floor and enter the data on the floor plan. Use the data
from the deployed floor for other identical floors.
For example, if the second floor of an office tower is laid out with
cubicle style offices with a perimeter of enclosed offices, and the third
floor is laid out in the same manner, both floors can have the same
installation profile for basestations.
All floors do not have the same layout.
If the floor plan varies from floor to floor, use the critical point method
to deploy each distinct floor. For more information, see
tool for deployment" (page
Do not underestimate the importance of changes in floor layout. Simple
changes in a room from a meeting room to a storage room can have
significant impact on the coverage from a basestation.
Multi floor coverage situations
The following situations require multi-floor coverage.
Atriums Cells in an atrium, as shown in
61), are usually larger than the cells of the remainder of the building. Use
the information in this section as a guide help you to plan an atrium. No
precise steps to follow when you deploy an atrium, but you must consider
several points. For more information, see
"Atriums" (page 60)
"High rise buildings" (page 61)
"Unusual conditions" (page 61)
Nortel Communication Server 1000
SIP DECT Fundamentals
NN43120-123 02.02 30 March 2010
Copyright © 2008-2010 Nortel Networks. All Rights Reserved.
264).
Figure 30 "An atrium" (page
"Unusual conditions" (page 61)
"Prepare the
.

Advertisement

Table of Contents
loading

Table of Contents