7.3 BATCH engineering
Switching over the BATCH client
The assignment of the BATCH client <-> BATCH server is generally made during configuration
in the engineering system. After reading in the process cell data, a BATCH client then operates
with the process cell project of the corresponding BATCH server.
If there is information on more than one process cell project on the BATCH server, a selection
dialog with all existing process cell projects is displayed on the BATCH client after selecting
the menu command Program > Read in new process cell . By selecting a process cell project,
you establish the connection to the BATCH server (and therefore also to the required process
cell project).
One BATCH server per project
Note
In the scenarios described above, the rule that there must be only one BATCH server per S7
project /multiproject still applies.
7.3.17

Downloading to the target system, changes

Global data blocks must be loaded
When delta loading in the CFC, you must ensure that the "Include user data blocks" option
button is selected.
You make this setting in the "S7 Download" tab when you load the S7 program in the CFC
from the BATCH configuration dialog or from the SIMATIC Manager.