8.5 Distributed multiproject engineering
Requirement
You have received the project of the CMP and the master data library as archive files.
Procedure
The required tasks you need to performed on the distributed engineering station are presented
below in chronological order.
1. If there is an AS project in the destination path with a name identical to the one in your
distributed multiproject, archive this project for later use and then delete it in the DMP.
2. Retrieve the project to the destination path of the distributed multiproject.
File > Retrieve > select file and then Open > select destination directory and then click OK
> OK > Do you want to remove the references to the multiproject? Yes > Yes
3. Restore the transfer master data library in the same directory. Open the retrieved project,
delete the "Batch process cell" object, remove the ISA-88 type definitions and adapt the
AS address (MAC address) as required. The configured S7 connections can remain in the
project. You can ignore system warnings relating to this.
– Select the project and then select the batch process cell > in the data window, right-click
– In the Plant view, select the folder of the batch process cell, right-click and select the
4. Include the project and the master data library in the distributed multiproject.
Select your multiproject folder, open the shortcut menu and select Multiproject > Insert into
Multiproject > Select the project or the master data library and click OK. Specify the inserted
library as the master data library.
5. Merge the subnets or synchronize the subnets with networks in the distributed project.
Select the multiproject folder, open the shortcut menu and click Multiproject > Adjust
Projects > In the dialog that opens, select the "Ethernet" subnet in the navigation window
and then "Execute". In the dialog that appears, select the corresponding subnet in the
multiproject and insert it into the "Merged" window with the right arrow. In the "Merged"
window, select the displayed folder to check if the subnet has been merged. Then click OK
> Apply.
6. To allow testing, configure an S7 connection from the AS to the OS.
Open NetPro > Select the CPU in the AS > Select a free position in the connection table,
open the shortcut menu and click "Insert New Connection" >. In the "Insert New Connection"
dialog, select the folder "In Multiproject: xxx", select the "WinCC Application" and click "OK"
> In the "Properties S7 Connection" dialog, under the connection path, select the local and
partner interface from the respective drop-down lists and click "OK" .
7. Insert the Batch process cell object into your project.
Select the multiproject folder in the plant view and click Insert New Object > Batch Process
Cell in the shortcut menu.
8. Type-define your batch process cell.
Select the top hierarchy folder and, in the shortcut menu, click "Object properties" > In the
"ISA-88 type definition" tab of the properties dialog, select "Process cell" as the object type
and click "OK". The folder of the batch process cell is given a light green background.
234
and select "Delete" in the shortcut menu.
shortcut menu command "Object properties" > In the "ISA-88 type definition" tab, select
"<neutral>" from the selection box and then > OK. The BATCH identifiers are remove
in all hierarchy subfolders.