BATCH Control Center
9.6 Batch Planning
Order of batch processing (Page 382)
9.6.2.2

Creating a new production order

Procedure in BatchCC:
1. Select an order category folder below the "Orders" folder.
2. Select the menu item Edit > New.
A dialog with two tabs, "General" and "Batches", opens.
3. Make the following settings for the production order in the "General" tab:
– Name of the production order
– Planned total batch quantity for the order
– Earliest start and latest end of the batches
4. You then have two options as to how you continue the configuration.
1st option
You do not want to create specific batches yet. Simply confirm the settings made up to now
with "OK" at this point.
Result: The production order is inserted as an object in BatchCC. Later, you can add
batches to this order and set the actual properties for each batch.
See also section: Adding batches to a production order (Page 354)
2nd option
You move on immediately to the "Batches" tab.
For further settings:
See section: Assigning batches to a production order (Page 351)