Displaying The Run Time Of A Batch - Siemens SIMATIC BATCH Operating Manual

Process control system pcs 7
Table of Contents

Advertisement

BATCH Control Center
9.6 Batch Planning
Result
Chained batches are displayed with a connecting line in the time window. By selecting the
batches and then the shortcut menu command "Cancel connection to predecessor", the
chaining is broken again.
Note
● Deleting chained batches can result in the interruption of batch chain.
Tips:
● You zoom the time scale by pressing the CTRL key and the right mouse button at the same
time.
● If you select a batch and the "Display" command in the shortcut menu, the time segment
associated with the batch is displayed in the time window. Information about shortcut menu
command: If the batch to be chained is displayed in the time segment by the "Display"
command, the chaining mode is lost. Instead, shift the time window until the batch to be
chained is visible in the time segment.
● If you select the batch and use the "Go to Predecessor" command in the shortcut menu,
you will jump to the predecessor in the time window.
9.6.2.12

Displaying the run time of a batch

Procedure in the BatchCC:
1. In the "Orders" folder in the BatchCC select the object "Batch" below the production order.
2. Select Edit > Properties from the menu.
The "Properties of <batchname>" dialog opens.
The run time calculated in the Recipe Editor for the control recipe based on the individual
steps is displayed in the "Run time" box.
Note
These batch run times can be used to optimize planning. Please remember that these times
are not exactly the same as the actual times required for batch control.