Install the USB Board

Installing the USB board is a cold-service operation. You must power off the server before
installing the USB board.
1.
Consider your first step.
If you are replacing the USB board, remove the faulty or obsolete USB board
first, then return to this procedure,
See
"Remove the USB Board" on page
If you are installing the USB board as part of another component's removal
or installation procedure, go to
2.
Connect the cable to the motherboard and the USB board.
Review this information and complete these prerequisites in this order.
3.
See:
"Install the PSU Duct" on page 240
Step
4.
109.
Step
4.
Install the USB Board
Servicing the USB Board
113

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Netra SPARC S7-2 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Table of Contents