The periodic command delay test works for the digital transmission line only. It triggers command delay tests
at a configurable interval. The actual command transmission is not affected.
SWT3000 > Configuration > System
Connection: digital 1/2
Address
SWT3000 > Configuration > Clock Synchronisation
Command periodic delay test mode
Command periodic delay test interval
170
At least one digital is selected
Transmitter/Receiver < 128
One side is master, the other side is slave
Not OFF at the master side (If interval is off, no auto-
matically loop test is triggered )