Installation Verification Test Overview

The installation verification test enables you to verify that the library's installation and configuration is
complete and functioning correctly. The installation verification test runs the following individual tests:
Library alignment test
Picker assembly test
I/E station assembly test
Get/Put test
Scanner fiducial test
These tests require that you log on as an admin or service user. The accessor assembly must be ready and
functional, and the library must be powered on. In addition, the library must be in an offline state, and at
least one scratch tape must be inserted in the I/E station.
The smaller library configuration will require about 1 hour and the larger configurations will require as long
as 4 hours to run the installation verification test. The time to complete individual tests on an twelve module
configuration is approximately:
Library alignment test - 45 minutes
Picker assembly test - 4 minute
I/E station assembly test - 7 minutes for each I/E station
Get/Put test - 2 hours and 45 minutes
Scanner fiducial test - 75 minutes
These times do not include debug or repair time.
Note
Scalar i6000 Installation Guide
309

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Scalar i6000 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

This manual is also suitable for:

Scalar i2000

Table of Contents

Save PDF