4 Repair
4.7.3 Replacement of gearbox axis 3
Continued
3
4
5
6
7
8
9
Refitting
The procedure below details how to refit gearbox axis 3.
1
2
3
4
5
Continues on next page
284
Action
Drain the oil from gearbox axis 3.
Remove the upper arm.
While the upper arm is resting on its side on
the floor, fit the lifting tool in the uppermost hole
of the gearbox.
CAUTION
The gearbox weighs 51 kg! All lifting equipment
used must be sized accordingly!
Secure the gearbox with a roundsling in an
overhead crane.
Remove the attachment screws securing the
gearbox to the upper arm.
Remove the gearbox and put it in a safe place.
Action
Make sure the o-ring is fitted to the gearbox.
Lightly lubricate the o-ring with grease.
CAUTION
The gearbox weighs 51 kg! All lifting equipment
used must be sized accordingly!
Fit a lifting tool in the uppermost hole of the
gearbox and secure it with a roundsling.
Fit two guide pins in two of the attachment
holes, parallel to each other.
Lift the gearbox on to the guide pins and push
it to its mounting position.
© Copyright 2009-2018 ABB. All rights reserved.
Note
Detailed in the section
Changing oil,
axis-3 gearbox on page
152.
Detailed in the section
Replacement
of the upper arm on page
Art. no. is specified in
Required
equipment on page
282.
Shown in the figure
Location of gear-
box axis 3 on page
282.
Note
xx0600003127
A : O-ring 3HAB 3772-92
Art. no. is specified in
Required
equipment on page
282.
Product manual - IRB 6620LX
3HAC035737-001 Revision: P
214.

Advertisement

Table of Contents
loading

Table of Contents