In certain territories you will break the law if you do not install a beacon before you travel on site/public highways,
make sure you comply with the local laws.
Be careful when you operate the machine with a beacon. The total height of the machine is increased when
the beacon is in the operating position.
1. Put the beacon on the cab roof. A magnetic base keeps the beacon in position.
A
Beacon
B
Plug
C
Socket
2. Put the plug into the socket.
3. Use the beacon switch in the cab to operate the beacon. The indicator light in the switch illuminates when
the beacon is operating.
Refer to: About the Product > Console Switches (Page 16).
58
A
Tracking strut
A
Figure 47.
Figure 48.
C
B
9831/1100-2
Operation
Preparing for Travel
58

Advertisement

Table of Contents
loading

This manual is also suitable for:

Js330Js370

Table of Contents