3.7.1

Prepare controller for commissioning

1. Power connection wiring
– Refer to the mounting instructions supplied with the drive controller to find help on
how to correctly design the power connections to match the requirements of your
device.
2. Wire the control connections
– In case of the application shown in illustration [3-2], switch-off positioning without
pre-switch off, wiring according to the
3. Inhibit controller: Set terminal X4/RFR to LOW level or open contact.
4. Connect USB diagnostic adapter.
5. Switch on voltage supply of the controller.
– Without motor operation: Connect external 24 V supply.
– With motor operation: Connect mains voltage.
If the green "DRV-RDY" LED is blinking and the red "DRV-ERR" LED is off, the controller is
ready for operation and commissioning can proceed.
Related topics:
Automatic restart after mains connection/fault...
LED status displays
Firmware ≤ 11.00 - DMS 8.0 EN - 10/2011
Phone: 800.894.0412 - Fax: 888.723.4773 - Web: www.clrwtr.com - Email: info@clrwtr.com
Commissioning of the "Switch-off positioning" technology application
External 24 V DC
Controller enable / reset error
CW rotat. quick stop / selection: switch-off pos. 1
CCW rotat. quick stop / selection: switch-off pos. 2
( 381)
L
8400 StateLine C | Reference manual
"Terminals
2" control mode makes sense:
+
supply
=
Stop function 1
Stop function 2
( 97)
Commissioning
X4
24E
24I
RFR
DI1
DI2
DI3
DI4
DO1
GIO
63