6-22 Star Remote System user interface
Figure 6-10 Example of a RLDPESPost level output
RLDPES
0
Quit
2
Post_
3
4
5
6
7
8
9
10
11 Disp
12
13
14
15
16
17
18
userid
TIME
hh : mm>
To conduct a test of the batteries in the RLD, operating company personnel
must enter the BATTERY TEST command. The following are responses to the
BATTERY TEST command:
The following figure provides an example of the RLDPESPost level showing
the BATTERY QUERY command for the posted RLD.
297-8353-550 Standard 05.01 March 2001
CM
MS
IOD
.
.
.
.
SysB
PM
4
STAR
0
STAR REM1 00 0 Istb Links_OOS: CSide 0 PSide 0 UMP OOS:0
Unit 0:
ISTb
Unit 1:
ManB
Drwr:
11 11 11 11 11 22 22 22 22 22 33 33 33
01 23 45 67 89 01 23 45 67 89 01 23 45 67 89 01 23 45
MM .M –– –– –– –– –– –o ss –– –– –– –– –– –– –– –– ––
If the test fails, a PES200 log is output and the system response to the
QUERYPES command at the RLD level and the MAP display at the
RLDPES level report the test failure.
If no faults exist, the MAP display message is A battery test may
reduce the battery capacity. Please confirm
("Yes", "Y", "No", or "N").
If a DCFAIL alarm is on, the system does not perform the test and the
following message is output: DCFAIL alarm is on. A battery
test cannot be done.
If an ACFAIL alarm was raised in the last 3 days, the following message is
output: Less than 3 days passed since the last AC
failure. Test anyway? Please confirm ("Yes", "Y",
"No", or "N").
If the RLD is out of service the following message is output: The RLD
is out of service.
Net
PM
CCS
Lns
.
.
4 SysB
M
ManB
OffL
0
10
0
0
/RG: 0
/RG: 0
A test message cannot be sent.
Trks
Ext
Appl
.
.
.
CBsy
ISTb
InSv
3
3
0
1
RG
Pref 0 Istb
Stby 1 InSv
3
1