Figure 3-9 Installing a LAN switch
Step 3 Connect the LAN switch power cable to the PDU2000.
----End
Follow-up Procedure
If a 24-port LAN switch is configured, one or two power modules need to be
installed for the LAN switch onsite. Insert the power module into the power slot of
the 24-port LAN switch and tighten the captive screws on the power module
panel.
Figure 3-10 Installing a power module for a 24-port LAN switch

3.4 Installing an ECC800-Pro Collector

Issue 02 (2021-05-12)
NO TE
The positions of power cable ports vary depending on the LAN switch models. Connect the
power cable based on the actual power port of the LAN switch.