Figure 4-49 Main control board of the NetCol8000-C150
(1) Main control board
● The main control board can be Arm7 or M4. The appearance varies with the
model delivered.
● The Arm7 main control board has S1 and S2 DIP switches, and the M4 main
control board has only the S2 DIP switch. The S1 DIP switch needs to be set for
the Arm7 main control board and does not need to be set for the M4 main
control board.
● The Arm7 main control board uses the software of V100R001, and the M4
main control board uses the software of V100R002.
● You need to set only the seventh toggle switch based on teamwork
requirements and leave other toggle switches in their default status.
Figure 4-50 NetCol8000 main control board
(1) Teamwork communications port 1
(3) S1 DIP switch of the main control board
Table 4-44 Operations of the DIP switch
Toggle
Switch
1
2
3
4
5
Issue 02 (2021-05-12)
NO TICE
Default
Value
OFF
OFF
ON
ON
OFF
Copyright © Huawei Technologies Co., Ltd.
4 Connecting Monitoring Cables to Devices
(2) Teamwork communications port 2
(4) S2 DIP switch of the main control board
Operations
Remaining in OFF
Remaining in OFF
Remaining in ON
Remaining in ON
Remaining in OFF