Summary of Contents for Huawei iMaster NetEco V600R021C10

  • Page 1 NetEco V600R021C10 Device Installation and Commissioning Guide (Data Center) Issue Date 2021-05-12 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Indicates a hazard with a medium level of risk which, if not avoided, could result in death or serious injury. Indicates a hazard with a low level of risk which, if not avoided, could result in minor or moderate injury. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 4 WebUI. ● Optimized and added the content related to the UPS. ● Optimized and added the content related to the chiller station. 2021-04-15 This issue is the first official release. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 5: Table Of Contents

    3.7.5 Installing a Temperature and Humidity Sensor (BOM Number: 33010346)..........34 3.7.6 Installing a Temperature and Humidity Sensor (BOM Number: 02312PBL)..........35 3.7.7 Installing a Region-type Water Sensor........................37 3.7.8 Installing a Location-type Water Sensor........................39 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 6 4.2.10 Connecting a Monitoring Cable to an iBOX......................88 4.3 Scenarios for Connecting the ECC800-Pro Outside the Smart Module............. 89 4.3.1 Preparing a Monitoring Cable............................89 4.3.2 ECC800-Pro..................................90 4.3.2.1 Product Configuration..............................90 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 7 6.1 Performing Basic Operations Before Adding Devices.................... 138 6.1.1 IP Address Preinstallation Planning.......................... 138 6.1.2 Obtaining the NetEco Software License......................... 138 6.1.3 Obtaining the Adapter Software Installation Packages..................139 6.1.4 Powering On a Server..............................140 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 8 6.4.4.1 Creating a Chiller Subsystem on the NetEco (Modbus-TCP Protocol)............193 6.4.4.2 Creating Refrigeration Station Devices on the NetEco...................194 6.4.5 Adding a UPS..................................195 6.4.5.1 Setting Monitoring Parameters for a UPS2000-G (over SNMP)..............195 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 9 6.5.2.2 Adding a Temperature and Humidity Sensor....................252 6.5.2.2.1 Setting Monitoring Parameters for a T/H Sensor (BOM Number: 33010346)........253 6.5.2.2.2 Creating a Temperature and Humidity Sensor on the NetEco..............253 6.5.2.3 Adding a Water Leakage Sensor..........................254 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd. viii...
  • Page 10 7.1.2.2 Routine Maintenance for the Smart U space manager................. 282 7.1.2.3 Routine Maintenance for Temperature Sensors....................282 7.1.2.4 Routine maintenance for the temperature and humidity sensor............... 282 7.1.2.5 Routine maintenance for the camera........................283 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 11 8.1 How Do I Handle Abnormal Door Control Status?....................321 8.2 How Do I Change the NetEco IP Address?........................ 321 8.3 Logging In to the NetEco App............................323 9 Acronyms and Abbreviations....................327 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 12: Safety Information

    The "NOTICE", "CAUTION", "WARNING", and "DANGER" statements in this document do not cover all the safety instructions. They are only supplements to the safety instructions. Huawei will not be liable for any consequence caused by the violation of general safety requirements or design, production, and usage safety standards.
  • Page 13 ● Keep irrelevant people away from the equipment. Only operators are allowed to access the equipment. ● Use insulated tools or tools with insulated handles, as shown in the following figure. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 14 Do not change the structure or installation sequence of equipment without permission. ● Do not touch a running fan with your fingers, components, screws, tools, or boards before the fan is powered off or stops running. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 15: Personnel Requirements

    Do not power on the equipment before it is installed or confirmed by professionals. 1.2 Personnel Requirements ● Personnel who plan to install or maintain Huawei equipment must receive thorough training, understand all necessary safety precautions, and be able to correctly perform all operations. ●...
  • Page 16 0°C. Handle cables with caution, especially at a low temperature. – Cables stored at subzero temperatures must be stored at room temperature for at least 24 hours before they are laid out. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 17: Installation Environment Requirements

    Install the equipment in an area far away from liquids. Do not install it under areas prone to condensation, such as under water pipes and air exhaust vents, or areas prone to water leakage, such as air conditioner vents, ventilation Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 18 Any violations must be promptly pointed out by the site manager or safety supervisor and the involved personnel should be prompted for correction. Personnel who fail to stop violations will be forbidden from working. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 19: Mechanical Safety

    Ensure that the wider end of the ladder is at the bottom, or protective measures have been taken at the bottom to prevent the ladder from sliding. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 20 D ANGER When removing a heavy or unstable component from a cabinet, be aware of unstable or heavy objects on the cabinet. ● Be cautious to avoid injury when moving heavy objects. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 21: Others

    UPS output voltage level or frequency. Doing so may affect the power supply to equipment. ● Exercise caution when setting battery parameters. Incorrect settings will affect the power supply and battery lifespan. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 22: Installation Preparations

    2.2 Tools and Instruments Before the installation, prepare the following common tools and transportation tools. Tools required vary with the actual installation scenarios. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 23 Step ladder (2 m) Phillips Phase sequence Flat-head screwdriver meter screwdriver (2–5 Adjustable wrench Socket wrench Hex key Box-end wrench (6″) M4/M6/M8/M12 M6/M8/M12 Torque wrench Solid wrench Cotton cloth Label (28 mm) (12#/13#/18#) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 24 Polyvinyl chloride Needle-nose Diagonal pliers RJ45 crimping (PVC) insulation pliers tool tape Crimping tool Wire strippers Hydraulic pliers Wire clippers Cable tie Multimeter Electroprobe Brush Claw hammer Vacuum cleaner Hacksaw Handsaw Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 25: Personnel Requirements

    Only trained and qualified personnel who fully understand basic safety precautions are allowed to install and operate a Smart Module. CA UTION Huawei will not be liable for any consequence caused by the violation of this document. Issue 02 (2021-05-12)
  • Page 26: Device Networking Solution Overview

    Center) 2 Installation Preparations The requirements are as follows: ● Customers' installation personnel must be trained by Huawei and understand how to install and operate a Smart Module. ● The number of installation personnel varies depending on the project progress and the installation environment.
  • Page 27 NetEco Device Installation and Commissioning Guide (Data Center) 2 Installation Preparations Figure 2-2 Flowchart for the installation and commissioning of NetEco devices Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 28: Installing Devices

    There are multiple types of monitoring components. Make installation plans based on the configurations. Figure 3-1 shows the installation positions for some monitoring components for your reference. Figure 3-1 Device layout in the network cabinet Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 29: Installing A Server

    Figure 3-2 Connecting a device ground cable 3.2 Installing a Server 3.2.1 Installing a TaiShan 200 Server Context Tools: Phillips screwdriver, ESD wrist strap Materials: TaiShan 200 server, guide rail, rubber plug Space required: 2 U Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 30 When the two mounting ears of the server come into contact with the mounting bars on the cabinet, tighten their captive screws to secure the server. See (2) in Figure 3-5. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 31: Installing A 2288X V5 Server

    The server uses dual power supplies. Connect the two power cables to different PDUs. ----End 3.2.2 Installing a 2288X V5 Server Context Tool: Phillips screwdriver Materials: 2288X V5 server, guide rail, rubber plug, screw Procedure Step 1 Install guide rails. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 32 Step 3 Align the two mounting ears of the server with the mounting bars of the cabinet and tighten the screws on the mounting ears. Figure 3-7 Installing a server Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 33: Installing A Lan Switch

    Step 2 Install the mounting ears delivered with the LAN switch and secure the LAN switch to the mounting bars in the front of the cabinet. NO TE This section describes only the installation method. The actual product appearance prevails. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 34: Installing An Ecc800-Pro Collector

    LAN switch onsite. Insert the power module into the power slot of the 24-port LAN switch and tighten the captive screws on the power module panel. Figure 3-10 Installing a power module for a 24-port LAN switch 3.4 Installing an ECC800-Pro Collector Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 35: Installing A Smart U Space Manager

    U Asset Label is 52273315. The smart U space manager consists of the following components. Figure 3-12 Smart U space manager appearance (1) Asset detection strip (2) U Asset Label (3) Main control box Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 36 Figure 3-13 Installing a smart U space manager (main control box attached to the top of the cabinet interior) (1) Fastener (2) UIM20A Expansion Module (3) Main control box (4) Asset detection strip (42 U detection point) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 37: Installing A Uim20A Expansion Module

    ----End 3.6 Installing a UIM20A Expansion Module Procedure Step 1 Secure a mounting ear to each of the two sides of the UIM20A expansion module using four M4 screws. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 38 Figure 3-16 Installing floating nuts Step 3 Secure the UIM20A expansion module to the cabinet by tightening the M6 screws on the left and right mounting ears clockwise. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 39: Installing Sensors

    ● The temperature sensor is installed in the middle of the cabinet door and is vertical from top to bottom after installation. ● NTC1–NTC3 of the T/H sensor must be placed in the cold air area, and NTC4–NTC46 must be placed in the hot air area. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 40: Installing A Hydrogen Sensor

    A hydrogen sensor is used to detect the hydrogen density indoors. It works with the hydrogen detection system. ● The hydrogen detection system is installed on the ceiling of the area to be detected. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 41: Installing The Hydrogen Detection System

    Procedure Step 1 Install four expansion bolts (M6x60) to the specified positions, align the four mounting ears of the hydrogen detection system with the expansion bolts, and tighten the M6 nuts. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 42 3-1, and connect the cable to (7). D ANGER Pay attention to the negative and positive polarities of the power supply. If the polarities are connected incorrectly, the device may be burned. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 43 Pin 1 (orange-white) RS485+ Pin 2 (orange) RS485- Pin 3 (green-white) 12V+ 12+ input Pin 4 (blue) Pin 5 (blue-white) Pin 6 (green) Pin 7 (brown-white) Pin 8 (brown) 12V- 12- input ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 44: Installing A Smoke Detector

    Step 1 Take out the smoke detector base and mark mounting holes for the base in the appropriate position. Figure 3-23 Mounting holes (unit: mm) Step 2 Drill holes and install expansion tubes. Install the smoke detector base to the top of the room. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 45: Installing A Temperature And Humidity Sensor (Bom Number: 33010346)

    Materials: temperature and humidity sensor, temperature and humidity sensor base Document: temperature and humidity sensor installation position diagram Procedure Step 1 Remove the front cover from the temperature and humidity sensor. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 46: Installing A Temperature And Humidity Sensor (Bom Number: 02312Pbl)

    Set the device address for a T/H sensor by operating the DIP switch on the sensor. Toggle switches 1–6 are used to set the device address, toggle switch 7 is reserved, and toggle switch 8 is used to switch the temperature display mode. The device Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 47 The numbers indicate the DIP switch settings of the T/H sensors. Figure 3-26 DIP switch settings for T/H sensors Step 3 Connect the communications cables to the T/H sensors. Figure 3-27 Cable connections to T/H sensors Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 48: Installing A Region-Type Water Sensor

    Procedure Step 1 Install the water detector near the collector and secure it using screws or other methods. Step 2 Connect the water detection cable to the conversion cable. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 49 Take protective measures when routing a water detection cable. Step 5 Tear off the protection paper on the rear of the fastener, then securely attach the fastener to the floor. Figure 3-31 Installing a fastener Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 50: Installing A Location-Type Water Sensor

    If multiple water detection cables need to be connected in series, connect the male connector of one cable to the female connector of another cable. ----End 3.7.8 Installing a Location-type Water Sensor Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 51 ● Prevent it against metal filings, grease, pipe paint, and other contaminants. Step 3 The location-type water sensor consists of a water leakage locator, tieline, and water leakage location cable, the connection diagram is as follows. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 52 Table 3-2 RJ45 cable wire sequence of the Tie line Definition Pin 1 (orange-and-white) RS485+ Pin 2 (orange) RS485- Pin 3 (green-and-white) 12VDC Pin 4 (blue) RS485+ Pin 5 (blue-and-white) RS485- Pin 6 (green) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 53: Installing The Video Management System

    IVS1800 in the cabinet. Procedure Step 1 Install hard disks. Use a PH2 screwdriver to remove the two black screws on the rear of the chassis cover, and take off the chassis cover. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 54 Figure 3-41 Fastening the screw on the panel and the screws on the hard disk tray Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 55 If the vents are blocked, change the guide rails. ● Huawei provides guide rails that can be adjusted from 500 mm to 800 mm for additional purchase if required for IVS1800 installation.
  • Page 56 Figure 3-45 Installing a guide rail Install a filler panel for guide rails. Fasten the M6 screws to install the filler panel for the guide rails. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 57 When the device is near the front door of the cabinet, fasten screws in hole groups 1 and 2; when the device is near the rear door, fasten screws in hole groups 2 and 3. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 58 Figure 3-49 Securing the device Step 3 Power on the device. Turn on the power switch. Check the indicators on the front panel of the device for its running status. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 59: Installing A C3220 Camera

    Procedure Step 1 Install an SD card. Remove the transparent cover using a Phillips screwdriver. Figure 3-50 Removing the transparent cover Gently insert the SD card into the SD card slot. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 60 During the installation, adjust the surveillance angle to avoid video image rotation after the installation. ● When adjusting the surveillance angle, pay attention to the position of the illuminator to prevent the illuminator from being blocked. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 61: Installing The M2121 Camera

    A camera and tools for installing it have been prepared. ● A network cable for connecting the camera to the LAN switch has been prepared. ● The LAN switch has been normally powered on. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 62 Paste the drilling sticker in the camera installation position. Ensure that the center of the sticker overlaps the center of the cable outlet on the wall. Figure 3-56 Determining the camera installation position Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 63 ● Face the cable outlet with BOTTOM on the camera base downwards to prevent water from flowing into the camera and cause damage to the camera. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 64: Installing The Access Management System

    Procedure Step 1 Mark the mounting holes using the access controller and marker, and drill holes using a hammer drill. Step 2 Unlock the access controller with the delivered key. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 65 Device Installation and Commissioning Guide (Data Center) 3 Installing Devices Figure 3-60 Unlocking an access controller Step 3 Use four screws to install the access controller on the wall. Figure 3-61 Installing an access controller ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 66: Installing An In-Room Double-Door Magnetic Lock

    (1) Door frame (2) Cutout template (3) Door panel Step 3 Remove the hoisting strip using the delivered hex key. NO TE Four hex socket screws need to be removed in this step. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 67 (2) in Figure 3-64. Step 6 Install the magnet. Take out the magnet, and knock the positing pins of the magnet into the magnet using a rubber mallet. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 68: Installing An In-Room Single-Door Magnetic Lock

    If the magnetic lock and the magnet do not work properly, check and troubleshoot the circuit. ----End 3.9.3 Installing an In-Room Single-Door Magnetic Lock Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 69 (3) Door panel Step 3 Remove the hoisting strip using the delivered hex key. NO TE Two hex socket screws need to be removed in this step. Figure 3-68 Removing a hoisting strip Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 70 Figure 3-69 Installing a magnetic lock Step 5 Remove the small cover from the magnetic lock, and route the cable out of the cable hole, as shown in Figure 3-70. Figure 3-70 Connecting cables Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 71 If the magnetic lock and the magnet do not work properly, check and troubleshoot the circuit. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 72: Installing A Fingerprint And Card Reader With A Keypad

    Step 5 Check that cables are correctly connected. Step 6 Secure the fingerprint and card reader with a keypad to the baseplate, as shown by (5) and (6) in Figure 3-74. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 73: Installing A Fingerprint And Card Reader

    (1) in Figure 3-76. Step 2 Mark the mounting holes using a marker, and drill holes using a hammer drill. Figure 3-75 Marking mounting holes (unit: mm) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 74: Installing A Card Reader With A Keypad

    Step 1 Remove the screws (set aside) from the card reader with a keypad and remove the baseplate, as shown by (1) in Figure 3-78. Step 2 Mark the mounting holes using a marker, and drill holes using a hammer drill. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 75 Step 6 Secure the card reader with a keypad to the baseplate, as shown by (5) and (6) in Figure 3-78. Figure 3-78 Installing a card reader with a keypad ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 76: Installing An Exit Button

    Remove screws from the emergency door release button using a Phillips screwdriver, as shown by (1) in Figure 3-79. Remove the glass panel of the emergency door release button, as shown by (2) and (3) in Figure 3-79. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 77 Install the glass panel of the emergency door release button, as shown by (2) and (3) in Figure 3-81. Tighten screws of the emergency door release button using a Phillips screwdriver, as shown by (4) in Figure 3-81. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 78: Connecting Monitoring Cables To Devices

    4.1.1.1 Server Ports (TaiShan 200 Server) The TaiShan 200 server (Model 2280) is a next-generation data center server developed by Huawei. Based on Huawei Kunpeng processors, the server features efficient computing, high security and reliability, and an open ecosystem. As the monitoring host of the NetEco management system, the server processes and analyzes data.
  • Page 79: Server Ports (2288X V5 Server)

    Used for connecting to an external device. 4.1.1.2 Server Ports (2288X V5 Server) The 2288X V5 server is a next-generation Huawei data center server that integrates patented technologies such as Dynamic Energy Management Technology (DEMT) and fault diagnosis & management (FDM). It features efficient computing, high security and reliability, and an open ecosystem.
  • Page 80 Used for connecting to an external device. iBMC remote Used for connecting to a PC to manage the management 2288X V5 server. port Server serial Used for connecting to an SMS modem or for port commissioning. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 81: Installing The Sms Modem

    Connect the other end of the power adapter to the universal conversion C1 socket. Connect the other end of the universal conversion C1 socket to the rPDU through a transfer cable (C13/C14 cable or China standard C13 cable). Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 82: Connecting Cables To The 4G Sms Modem

    The following figure shows the ports on the 4G SMS modem. Figure 4-4 Ports on the 4G SMS modem (1) SIM card slot (2) USB 2.0 port (3) External antenna port (SMA port) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 83 Blinks at intervals of 200 ms The modem is transmitting data. The modem is powered off. NO TE For details about how to connect the modem, see the product manual delivered with the modem. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 84: Scenarios For Connecting A Lan Switch

    4.2 Scenarios for Connecting a LAN Switch 4.2.1 Switches 4.2.1.1 Introduction to Switches (S5335-S24P4X) Exterior and interior Figure 4-5 Appearance of the S5335-S24P4X Table 4-5 S5335-S24P4X description Description Twenty-four 10/100/1000 BASE-T Ethernet electrical ports Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 85 Supported power module: 1000 W AC PoE power module (PAC1000S56-CB) Power module slot 2 NOTE Supported power module: 1000 W AC PoE power module (PAC1000S56-CB) Item lists technical specifications of the S5335-S24P4X. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 86 ● High-voltage DC input: 190–290 V DC Maximum power ● Without PoE: 65 W consumption ● Full PoE load: 847 W (PoE: 720 W) (100% traffic, full fan speed) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 87 10 km. Storage –40°C to +70°C temperature range Noise at room < 58.9 dB (A) temperature (27°C, sound power) Relative humidity 5%–95% RH (non-condensing) Operating 0–5000 m altitude Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 88: Introduction To Switches (S5735-S24P4X)

    ● 1 m and 3 m SFP+ high-speed cables ● 3 m and 10 m SFP+ AOC cables ● 0.5 m and 1.5 m SFP+ dedicated stack cables (used for zero- configuration stacking) One console port Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 89 Common mode: ±7 kV (The maximum voltage is ±10 kV, surge protection and the device is not damaged.) Power port surge ● Differential mode: ±6 kV; common mode: ±6 kV protection Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 90 (100% traffic, full speed of fans) Typical power 51 W consumption (30% traffic) ● Tested according to the ATIS standard ● EEE function enabled ● No PoE power consumption Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 91: Connecting A Monitoring Cable To The Neteco

    ● EMC certification certification ● Safety certification ● Production certification Item Code 98010940 4.2.2 Connecting a Monitoring Cable to the NetEco iMaster NetEco V600R021C10 Management System Wiring For details, see Diagram . Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 92: Connecting The Video Management System Cable

    Step 2 Connect the other end of the network cable to the Ethernet port on the LAN switch. ----End 4.2.4 Connecting the Smart Cooling Product Monitoring Cable Prerequisites A network cable used for monitoring is prepared. Context When NetCol5000-C(065, 080), NetCol5000-A050/A042/A035/A020/C030/C070/ C150, NetCol8000-A060/A120, or FusionCol8000-E220/E240/E400/C080/C210 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 93 For NetCol5000-C(065, 080), open the rear door, and connect one end of the network cable to the FE port on the main control board of the smart cooling product. Figure 4-7 NetCol5000-C(065, 080) main control board (1) Main control board Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 94 C070, NetCol8000-C150, NetCol8000-A060/A120, and FusionCol8000-E220/ E240/E400/C080/C210, open the rear door, and connect one end of the network cable to the COM/FE port on the main control module of the smart cooling product. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 95: Connecting The Ups Monitoring Cable

    Step 1 Connect one end of a network cable to the Ethernet port on the SNMP card of the UPS2000-G/UPS2000-H. Figure 4-11 Ethernet port (1) Ethernet port Step 2 Connect the other end of the network cable to the Ethernet port on the LAN switch. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 96: Connecting The Ups5000-A Monitoring Cable

    Figure 4-14 FE port on the UPS monitoring module of the 300 kVA UPS and models with higher capacities (1) FE port Step 2 Connect the other end of the network cable to the Ethernet port on the LAN switch. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 97: Connecting A Monitoring Cable To The Ups5000-E/Ups5000-H/Ups5000-S

    Procedure Step 1 Connect one end of the network cable to the FE port on the monitoring interface unit. Figure 4-15 Monitoring interface unit of the SmartLi (1) Monitoring interface unit Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 98: Connecting The Pdu8000 Monitoring Cable

    Prerequisites A network cable used for monitoring is prepared. Procedure Step 1 Connect one end of the network cable to the FE communications port on the SMU02C in the MTS9604B-N20B1/MTS9606B-N20C2 cabinet. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 99: Connecting A Monitoring Cable To Tp483000D/Tp482000B

    Step 1 Connect one end of the network cable to the PoE port on the iBOX. Step 2 Connect the other end of the network cable to the Ethernet port on the LAN switch. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 100: Scenarios For Connecting The Ecc800-Pro Outside The Smart Module

    Figure 4-19 Preparing a cord end terminal Preparing the RS485 Monitoring Cable Figure 4-20 shows how to prepare a cord end terminal for the ECC800-Pro collector. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 101: Ecc800-Pro

    Configuration 2: two power modules and one main control module. NO TE ● In configuration 1, install a filler panel in slot 2. ● In configuration 2, install power modules in slots 1 and 2. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 102 7.5 kg (dual power supplies + main control module) Color Black Installation requirements Can be installed in a 1 U space in a standard 19-inch cabinet Environmental protection RoHS5, REACH, WEEE Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 103 (AC_INPUT1 and AC_INPUT2) and two DC output ports (DC_OUT1 and DC_OUT2). Table 4-11 provides the power port pin definitions. Table 4-11 Power port pin definitions Port Type Description sequence Pin1 Pin2 Pin3 Pin1 48V+ Pin2 48VGND Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 104: Main Control Module

    The WLAN port is reserved and cannot be connected to a WLAN antenna for WLAN communication. Figure 4-24 ECC800-Pro main control module (side view) (1) SIM card slot (2) Micro SD card slot (reserved) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 105 AIDI_1 to AIDI_3 are full-function AIDI ports, and AIDI_4 to AIDI_5 are simplified AIDI ports without type identification. ● The power supply can be switched on or off and is on by default. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 106 ● You can insert a USB flash drive to export historical data and configuration files and import configuration files. SW button ● Restores the default IP address, factory settings, and user information. ● Supports RF_Z (802.15.4) networking. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 107 There are four GE ports, that is, two WAN ports (WAN1 and WAN2) and two LAN ports (LAN1/POE and LAN2/POE). Table 4-15 GE port pin definitions Item Description Pin1 GE1+ sequence Pin2 GE1- Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 108 ● Steady on: The 12 V DC output is normal. ● Off: No 12 V DC output is provided. Table 4-17 COM3/12V port pin definitions Item Description Pin1 RS485+ sequence Pin2 RS485- Pin3 12V DC_OUT Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 109 6 and Pin 7 can detect the output status of passive dry contact type sensors. Pin 3 and Pin 7 can detect temperature sensors. Table 4-19 AIDI_1, AIDI_2 and AIDI_3 ports pin definitions Item Description Pin1 Type_1 sequence Pin2 Type_2 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 110 ● Steady on: The 12 V DC output is normal. ● Off: No 12 V DC output is provided. Table 4-21 USB port pin definitions Item Description Pin sequence Pin1 Pin2 Pin3 Pin4 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 111 The RF_Z indicator is network RF_Z pairing mode, press and hold the blinking at super (802.15.4) button for 3s to 5s to enter the short intervals. pairing wireless network pairing mode. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 112: Power Module

    1s and then off for 1s). Blinking at The converter application short program is being loaded (the intervals indicator blinks at 4 Hz, on for 0.125s and then off for 0.125s). Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 113 0.5 Hz, on for 1s and then off for 1s). Fault Steady on The converter locks out due to indicator output overvoltage. The converter delivers no output due to internal faults. The converter is working properly. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 114: Uim20A Expansion Module

    Table 4-25 UIM20A expansion module specifications Item Specifications Width 120 mm Depth 200 mm Height 43 mm Operating –30°C to +65°C temperature Installation Installed in a 19-inch rack requirement Environmen RoHS5 protection Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 115 The following table describes the pin assignment for ports COM1/AIDI_1 to COM8/AIDI_8. Table 4-27 Pin assignment for ports COM1/AIDI_1 to COM8/AIDI_8 Item Description Pin1 RS485+ sequence Pin2 RS485- Pin3 Pin4 RS485+ Pin5 RS485- Pin6 Pin7 Pin8 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 116 Blinking at super short intervals for 0.5s and then off for 0.5s; last 10s (blinking at super short intervals: 10 Hz, on for 0.05s and then off for 0.05s) Steady A system fault alarm is raised. The system is normal. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 117: Connecting A Monitoring Cable To The Uim20A Expansion Module

    CH1 or CH2 terminal on the right of the access controller in the following figure. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 118 Connecting Cables to the Exit Button Figure 4-29 shows the cable connections to the access controller and exit button, using the cord end terminal to crimp the cable. Figure 4-29 Connecting cables to the exit button Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 119 COM port on the ECC800-Pro collector. The following table shows the pin mapping for the RS485 port and the COM port. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 120 ● The cable installation sequences shown in the following figure are for reference only. If any differences exist between the wiring diagram and this figure, the wiring diagram prevails. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 121 4-34. Route the other end of the cable along the cable trough inside the access controller and then out of the cable outlet, and connect it to the power supply to receive power. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 122 Related Information Table 4-34 Card reader and key terminal definition Terminal Identity Definition Key input R-AL Card reader pry signal input R-BP Control card reader buzzer Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 123 Table 4-37 Power terminal definition Terminal Identity Definition LK-P +12V Lock the power input + 12 V Lock the power input - Battery + Battery - +12V Controller + 12 V DC power input Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 124 Outdoor Cable, UL 25030393 Electric Cable, 300V/500V, 60227 IEC Cable from the emergency door release button to the 53(RVV), 2x0.75mm , Black(2Cores: access controller Brown, Blue), 6A, Flat Outdoor Cable, CCC, CE Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 125: Connecting A Monitoring Cable To The Door Status Sensor

    Procedure Step 1 Open the door status sensor, connect two cables, as shown in Figure 4-35. Figure 4-35 Connecting a monitoring cable to the door status sensor Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 126: Connecting Cables To Sensors

    4.3.6 Connecting Cables to Sensors 4.3.6.1 Connecting Cables to Sensors If the ECC800-Pro collector is connected to the following types of sensors, connect cables to the devices by referring to Figure 4-36. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 127: Connecting The Temperature Sensor Monitoring Cable

    Connect the other end of the network cable to the NTC1~3 or NTC4~6 port on the temperature and humidity sensor. Step 2 Connect the temperature and humidity sensor to the UIM20A expansion module. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 128: Connecting A Monitoring Cable To The Hydrogen Detection System

    Step 2 Short-circuit core wires 1 and 8 on the other end of the network cable. Step 3 Connect the core wires of the network cable to the cables for the smoke sensor, based on the mappings in Table 4-41. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 129: Connecting A Monitoring Cable To A Temperature And Humidity Sensor

    Connect the T/H sensor (BOM number: 02312PBL) to the RJ45 port. Figure 4-37 Interface for the T/H sensor network cable Table 4-42 Network cable wire sequence Definition pin1 RS485 (A) pin2 RS485 (B) pin3 V+12V input pin4 pin5 pin6 Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 130: Connecting A Monitoring Cable To The Region-Type Water Sensor

    Step 2 Connect the other end of the network cable to the live COM port on the ECC800- Pro or the UIM20A expansion module. ----End 4.3.7 Connecting the Smart Cooling Product Monitoring Cable 4.3.7.1 Connecting the NetCol5000 Monitoring Cable Prerequisites A network cable used for monitoring is prepared. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 131 ● The COM port of NetCol5000-C(065, 080) is on the main control board at the smart cooling product rear doors. Figure 4-38 NetCol5000-C(065, 080) main control board (1) Main control board Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 132 A035 and NetCol5000-A025 are on the main control modules at the smart cooling product rear doors. The NetCol5000-A042 is used as an example to show the position of the main control module. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 133 J73 on the main control module in NetCol5000-A020/NetCol5000-C030. NO TE The following figure shows the pin sequence of the network cable that connects to the J73 communications port. Figure 4-42 Pin sequence of a network cable Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 134 (3) S1 DIP switch of the main control board (4) S2 DIP switch of the main control board Table 4-43 Operations of the DIP switch Toggle Default Value Operations Switch Remaining in OFF Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 135: Connecting The Netcol8000 Monitoring Cable

    FusionCol8000-E220/E240/E400/C080/C210 connects to the NetEco over Modbus RTU, connect cables by referring to this section. ● The following figure shows the pin sequence of the network cable. Figure 4-45 Pin sequence of a network cable Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 136 Figure 4-46 Main control board of the NetCol8000-A050 (1) Main control board Figure 4-47 Main control board of the NetCol8000-A100 (1) Main control board Figure 4-48 Main control board of the NetCol8000-C070 (1) Main control board Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 137 (4) S2 DIP switch of the main control board Table 4-44 Operations of the DIP switch Toggle Default Operations Switch Value Remaining in OFF Remaining in OFF Remaining in ON Remaining in ON Remaining in OFF Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 138: Connecting A Monitoring Cable To A Chiller

    Step 1 Connect one end of the network cable to the COM port on the chiller. Step 2 Connect the other end of the network cable to the COM port on the ECC800-Pro collector or the UIM20A expansion module. ----End 4.3.9 Connecting the UPS Monitoring Cable Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 139: Connecting A Monitoring Cable To The Ups2000-G (Modbus)

    4.3.9.2 Connecting a Monitoring Cable to the UPS5000-A Prerequisites A network cable used for monitoring is prepared. Procedure Step 1 Connect one end of a network cable to the COM port of the UPS5000-A. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 140: Connecting A Monitoring Cable To The Ups5000-E/Ups5000-S

    Step 2 Connect one end of the network cable to the COM port on the ECC800-Pro collector or the UIM20A expansion module. ----End 4.3.9.3 Connecting a Monitoring Cable to the UPS5000-E/UPS5000-S Prerequisites A network cable used for monitoring is prepared. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 141: Connecting The Pdc Monitoring Cable

    PDU2000-32-1PH-20/4-M1 Prerequisites A network cable used for monitoring is prepared. Procedure Step 1 Connect one end of the network cable to the COM1 port or the COM2 port on the PDU2000. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 142: Connecting A Monitoring Cable To An Hpxpdu2000-16-3Ph-24-6-M1

    PDU2000. Figure 4-58 PDU2000 ports Connect the other end of the network cable to the COM port on the ECC800- Pro collector or the UIM20A expansion module. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 143: Connecting The Fresh Air Unit Monitoring Cable

    Figure 4-59 Positions of pins 81 and 83 Step 2 Connect the other end of the network cable to the COM port on the ECC800-Pro collector or the UIM20A expansion module. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 144: Scenarios For Connecting The Ecc800-Pro In The Smart Module

    Step 1 For details about how to connect monitoring cables to the ECC800-Pro, see the Smart Modular Data Center Management System Wiring Diagram. NO TE The onsite wiring diagram of the management system prevails. The method described in this section is for reference only. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 145: Checking The Installation

    The door locks function normally. The exteriors and interiors of the cabinets (including the front door, rear door, and sides of each cabinet) are clean. No dirt, damage, or fingerprint is allowed. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 146: Checking The Installation Of Components In The Cabinet

    A protective cover is installed for the power module if the power module is configured with a protective cover. 5.3 Checking the Installation of Power Cables and Ground Cables Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 147: Checking The Connection Of Signal Cables

    The optical fibers must be sheathed using corrugated pipes at outsides of cabinets. Both ends of the pipes must be fastened. The edges are smooth or be processed for cutting prevention. No other cables are laid on optical fibers. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 148 The trunk cables are laid out smoothly without any tangling. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 149: Adding Devices

    6.1.2 Obtaining the NetEco Software License The NetEco software license is not provided together with software to the customer. Therefore, obtain the NetEco software license in advance. Obtain the license from the Huawei's enterprise support website. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 150: Obtaining The Adapter Software Installation Packages

    OpenPGP Signature Verification Guide . If the software package according to the fails to pass the verification, do not use the software package and contact Huawei technical support. Before a software package is used in installation, its digital signature also needs to...
  • Page 151: Powering On A Server

    Step 4 Press the power button on the chassis of the server to power on the server. NO TE After the server is started properly, the button/indicator of its power switch is displayed green. Figure 6-1 Power button on the 2288X V5 server Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 152: Logging In To The Neteco Client

    Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 153: Loading The Neteco Software License

    The time required for the installation is related to the number of adapters. Wait for the installation to complete. 6.1.8 Adding a Management Domain 6.1.8.1 General Operation: Adding a Management Domain This section describes how to create a management domain. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 154: Example: Adding A Smart Module

    ----End 6.1.8.2 Example: Adding a Smart Module This section describes how to create a module in the root node, subnet, equipment room, container, or site management domain. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 155 Step 6 Modify Management Info of the smart module as required or retain the default values. Step 7 Click on the toolbar to save the settings. ----End Follow-up Procedure Perform the following operations on the Planning Configuration page as required. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 156 Parent Name and Control Type, and you do not need to manually set them, you only need to set Name. 4. In the upper area of the current page, click Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 157: Example: Adding A Container

    3. You can select the text style, font size, color, and text background in the Component Info area on the right. 4. In the upper area of the current page, click Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 158: Adding Devices

    In area 2, click the Device tab, select a device type from the drop-down list box, and select the device to be added. Drag the selected device icon to area 3. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 159: Scenarios For Connecting The Ecc800-Pro In The Smart Module

    Select Running Control and click Blink. In the actual environment, you will see that the smart U space manager blinks to ensure that the device location in the view is consistent with that in the smart module. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 160: Adding Asset Information On The Neteco

    On the Asset Inventory page, you can click New Device and specify the asset information to register a single asset. In the Import dialog box, click Asset registration template.xls to download the template. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 161 After assets are registered, you can view the assets on the Asset Inventory page. Enter any information about registered assets and click Search to search for assets. Figure 6-7 Viewing registered assets ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 162: Icooling Energy Management

    Submit. Figure 6-8 Setting running parameters Step 4 Choose Monitoring > Cooling > Running Parameters. In the Cooling Capacity Management area, set the parameters related to cooling capacity management Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 163: Setting Icooling Parameters On The Neteco

    Select the smart cooling products to function as the data sources and click Confirm. NO TE You can enter a smart cooling product name in the search box for search. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 164 OFF indicates that the iCooling energy saving mode is not enabled, and ON indicates that the mode is enabled. When the iCooling energy saving mode is enabled, you cannot configure the terminal smart cooling product, import configuration parameters, or import algorithm parameters. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 165: Viewing Icooling Energy Efficiency On The Neteco

    Step 3 Select the required management domain from the drop-down list in the upper- right corner of the page. Step 4 View Overall Running Status, PUE(Hours), Energy Saving and Total Consumed Energy, and Running Overview. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 166: Optional) Viewing A Temperature Map On The Neteco

    When short messages need to be sent, you need to set parameters for notifications sent in SMS messages and commission the settings to ensure that SMS messages can be properly sent. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 167 Step 2 Choose System > System Settings > Notifications from the main menu. Step 3 In the navigation tree on the left, choose SMS Modem Settings and set interworking parameters of the SMS modem. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 168 . The recipient mobile number is used only for testing. When this parameter is left blank, the test button is unavailable. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 169: Scenarios For Connecting The Lan Switch

    Browser: Internet Explorer 9 or later, FireFox 43 or later, and Chrome 41 or later ● The IP addresses, subnet masks, and gateways for the PC and iBOX are in the same network segment. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 170 WebUI functions but has potential risks. Therefore you are advised to update the security certificate as soon as possible. On the iBOX WebUI, choose System Settings > Batt. String Config, and set Batt. String Config. Figure 6-11 Batt. String Config Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 171 If multiple iBOXs are connected in parallel, set Configuration iBOX parallel communication switch to Yes, set Number of iBOX configured under each UPS, and set the IP address for each iBOX. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 172 TLS Config communication On the System Settings page, set Alarm Parameters, Time, IP Address, Certificate Management, Battery Curve, NetEco, and Parallel Net Join Configuration Information. Figure 6-13 Alarm Parameters Figure 6-14 Time Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 173 NetEco Device Installation and Commissioning Guide (Data Center) 6 Adding Devices Figure 6-15 IP Address Figure 6-16 Certificate Management Figure 6-17 Battery Curve Figure 6-18 NetEco Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 174: Creating An Ibox Collector On The Neteco

    ● You have created a management domain for the device to be added on the Planning Configuration page. Context The following operations describe how to manually create an iBOX. ● UPS_Huawei_UPS5000E_V1R3C00C01_MODBUSTCP Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 175 NOTE The port number is 502 by default. You can modify the port number based on requirements. Device Address Fixed value: 2. NOTE This parameter does not need to be configured. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 176 Timeout duration for a connection test. The default value is Step 8 Click on the toolbar to save the device information. Step 9 Click Connection test to start the connection test. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 177: Ibox And Ibat Networking

    ● Blinking at long intervals: The indicator is on for 1s and then off for 1s alternately. ● Blinking at super short intervals: The indicator is on for 0.05s and then off for 0.05s alternately. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 178: Adding A Video Management System

    ● The camera IP address and the IVS service IP address must be in the same network. ● For details about the northbound IP address, see "Overview of Southbound and Northbound iMaster NetEco Product Documentation (DC) (V600R021C10_xx) . Network Isolation" in Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 179: Obtaining Video Management System Documents

    Table 6-4 Documentation for commissioning Component Document C3220/M2121 Huawei C Series SDC 8.0.1 Product Documentation IVS1800 IVS1800 8.1.0 Product Documentation 6.4.2.2 Commissioning a C3220/M2121 Camera Prerequisites If multiple cameras are accessed, retain the connection of one camera and disconnect connections from other cameras.
  • Page 180 WebUI cannot be opened. 1. Choose Tools > Internet Options. The Internet Options dialog box is displayed. 2. Click the Advanced tab. 3. Select Use TLS 1.1 or Use TLS 1.2. 4. Click OK. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 181 Preview the site situation in real time and check the camera coverage through videos. Adjust the lens if necessary. On the View tab page, click the Network/Time tab to access the Network/ Time tab page. Figure 6-21 Setting the IP address Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 182 On the View tab page, click the General tab to access the General tab page. Select Video and set the parameters, as shown in the following figures. Figure 6-22 Setting primary stream parameters Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 183 The encoding process of each slice is independent of each other. Therefore, the camera can encode and decode multiple slices in parallel, improving encoding and decoding performance. This parameter is selected by default. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 184 The bit rate range depends on the selected resolution. Bit rate value Average bit rate when Bit rate type is set to Constant bit rate. The bit rate range depends on the selected resolution. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 185: Commissioning The Ivs1800

    6.4.2.3.1 Setting Parameters on the IVS1800 WebUI Prerequisites For details about the IVS1800 hardware description and installation, see the Quick Start in the corresponding IVS1800 product documentation. For details about the Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 186 Figure 6-24 OMU portal home page Step 3 Configure disk initialization. NO TE Recording data can be stored only after you install and initialize the disks. Choose Local Configuration > Local Disk. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 187 Internet browser, and log in to the OMU portal system. (Optional) Configure the NTP synchronization. After setting The NTP clock source server to Yes, set the IP address of the NTP server. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 188 Set Module Name to OMU and click Search. In the search result, click Edit in the row where the value of Parameter Name is OMUNNatIP and set Value to the MUNNatIP address of the MU. Click Save. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 189 Choose User Management > Add User. NO TE When creating a user, you can select Enable account validity period and set Valid from and Valid to to set the account validity period for the created user. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 190: Setting Parameters On The Iclient

    Method 2 1. Log in to the OMU portal, choose Local Configuration > Basic Configuration, and view Current version. 2. Log in to https://support.huawei.com/enterprise/, and search for and choose iClient. In the search result, click the Software Download tab, click the version and patch number corresponding to the current version, and download the software package as required.
  • Page 191 "Reference Documentation" section. View the corresponding section. On the home page of the iClient, click Device Management. Right-click an IVS1800 and choose Camera Access. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 192 Device Installation and Commissioning Guide (Data Center) 6 Adding Devices Figure 6-32 Camera Access Select Auto Batch Access and click Start. Set the IP address segment. Figure 6-33 Setting an IP network segment Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 193 If the live video can be properly played, the camera is successfully connected. Step 3 Configure a recording policy. Log in to the iClient and click Device Management on the home page. Right-click an IVS1800 and choose Storage Management. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 194 Log in to the iClient and click Device Management on the home page. Right-click an IVS1800 and choose Storage Management. Click the Server Recording Plan tab. The tab page for configuring a server recording plan is displayed. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 195: Configuring Camera Parameters On The Neteco

    Step 3 In the navigation tree on the left, choose Video Surveillance Subsystem. Step 4 Click Create on the right of the page. The Creating a Video Subsystem dialog box is displayed. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 196 VCN is 9900. ● The IVS server supports two access modes: eSDK and IVS. The default port number of the eSDK is 9900, and the default port number of the IVS is 18531. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 197: Adding Cameras By Automatic Discovery On The Neteco

    6.4.2.5 Adding Cameras by Automatic Discovery on the NetEco This section describes how to quickly add an online camera that is not in any management domain to a management domain using the automatic discovery function provided by the system. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 198: Setting Video Playback On The Neteco

    6.4.2.6 Setting Video Playback on the NetEco Only cameras managed by the video subsystem support the video playback function. By setting video playback, you can view videos that are manually recorded. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 199: Adding A Smart Cooling Product

    6.4.3 Adding a Smart Cooling Product 6.4.3.1 Setting Monitoring Parameters for the Smart Cooling Product (over Modbus-TCP) The method of setting monitoring parameters for NetCol5000-C(065, 080), NetCol5000-A035/A042/A050/C025/C030, NetCol8000-A060/A120, and FusionCol8000-E220/E400/C080/C210 are the same. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 200 The encryption mode must be the same as it on the NMS. WARNING After the Encryption operation CBC parameter is set, the system automatically restarts. Exercise caution when performing this operation. Figure 6-40 Warning dialog box Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 201 Step 4 Return to the home screen, and choose Settings > Comm Settings > WAN IP Settings or Settings > Comm Settings > IP Settings. Table 6-10 Parameters for WAN IP settings Parameter Setting IP address Set according to the actual plan. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 202: Creating A Smart Cooling Product On The Neteco

    Step 7 Click the device. In the device parameter area on the right, set device parameters according to the following table. Table 6-11 Modbus-TCP device parameter description Parameter Description Managed Device name Object Name Set the IP address of the device. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 203 NetEco is changed on the server. 4. Click OK. Timeout Timeout duration for a connection test. The default value is 3s. Period Step 8 Click on the toolbar to save the device information. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 204: Adding A Refrigeration Station

    Port number of the chiller subsystem The default port number is 502. You can change the port number as required. Device Address Set this parameter to the address set on the device. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 205: Creating Refrigeration Station Devices On The Neteco

    Step 9 Click Connection test to start the connection test. ----End 6.4.4.2 Creating Refrigeration Station Devices on the NetEco This section describes how to add refrigeration station devices (chiller group control, for example) on the NetEco. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 206: Adding A Ups

    6.4.5.1 Setting Monitoring Parameters for a UPS2000-G (over SNMP) Before connecting UPS2000-G to NetEco, you should set the IP address on the UPS2000-G, add user and set permissions on the WebUI of UPS2000-G. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 207 Step 3 Add a user and set user permissions on the WebUI (WebUI 1). Choose System Settings > SNMP Settings. In the SNMP area, set SNMP Version to SNMPv3 and SNMP Port to 161, and click Submit. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 208 In the displayed SNMP Trap dialog box, set SNMP trap parameters, and click Confirm. – Enter the IP address of the NetEco server in the Trap Target Address text box. – Set Trap Port to 162. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 209 – You are advised to set MD5/SHA Password and DES/AES Password to different values. – MD5 is an insecure protocol. SHA is recommended. DES is an insecure protocol. AES is recommended. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 210 In the displayed Add SNMP Trap dialog box, set related parameters and click Add. – Enter the IP address of the NetEco server in the Trap Address text box. – Set Trap port to 162. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 211: Setting Monitoring Parameters For A Ups2000-H (Over Snmp)

    – You are advised to set MD5/SHA password and DES/AES password to different values. – MD5 is an insecure protocol. SHA is recommended. DES is an insecure protocol. AES is recommended. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 212 In the displayed SNMP Trap dialog box, set SNMP trap parameters, and click Confirm. – Enter the IP address of the NetEco server in the Trap Target Address text box. – Set Trap Port to 162. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 213 – You are advised to set MD5/SHA Password and DES/AES Password to different values. – MD5 is an insecure protocol. SHA is recommended. DES is an insecure protocol. AES is recommended. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 214 In the displayed Add SNMP Trap dialog box, set related parameters and click Add. – Enter the IP address of the NetEco server in the Trap Address text box. – Set Trap port to 162. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 215: Setting Ups5000 Monitoring Parameters (Over Snmp)

    In the SNMPv3 area, click Add. In the displayed SNMPv3 dialog box, set SNMPv3 parameters, and click Confirm. – You are advised to set MD5/SHA password and DES/AES password to different values. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 216 In the displayed SNMP Trap dialog box, set SNMP trap parameters, and click Confirm. – Enter the IP address of the NetEco server in the Trap Target Address text box. – Set Trap Port to 162. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 217 Figure 6-56 Setting SNMP parameters_02 Set User name, MD5/SHA Password, and DES/AES Password for the user to be added. – You are advised to set MD5/SHA password and DES/AES password to different values. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 218 Choose System Settings > iBOX Settings > Basic Parameters or choose Monitoring > iBOX Param. > Basic Param. and verify that iBOX logical start addr is set to 2 for the UPS5000. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 219: Setting Ups5000 Monitoring Parameters (Modbus Tcp)

    – Set parameters on the WebUI based on the actual situation. For details, see "Operation (UPS5000 WebUI 1)" or "Operation (UPS5000 WebUI 2)" in the following table. – A non-SSL connection has security risks. You are advised to select the secure SSL connection. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 220 Choose System Settings > iBOX Settings > Basic Parameters or choose Monitoring > iBOX Param. > Basic Param. and verify that iBOX logical start addr is set to 2 for the UPS5000. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 221: Creating A Ups On The Neteco

    The port number is 502 by default. You can modify the port number based on requirements. Device Address Set this parameter to the address set on the device. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 222 Parameter Description Managed Object Device name Name Set this parameter to the device IP address. Port Set this parameter to the port number of the device. (set to 161 by default) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 223 Set this parameter to the privacy protocol set on the device. The default selection is AES128. Support CBC_DES, AES128, AES192, and AES256 agreement. NOTE DES is an insecure protocol. AES is recommended. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 224: Adding A Pdu

    The preset user name and password for the PDU8000 are admin and 000001 respectively. To ensure access security, change the password upon the first login. Step 3 Tap Communication. Check that IP address assign is set to Manual. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 225: Setting Pdu8000 Monitoring Parameters (Modbus Tcp)

    Before connecting the PDU8000 to the NetEco, set monitoring parameters such as the IP address on the PDU8000. Procedure Step 1 Tap Settings on the PDU8000 home screen. Step 2 Enter the PDU8000 user name and password and tap Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 226: Creating A Pdu On The Neteco

    Step 7 Click the device. In the device parameter area on the right, set device parameters according to the following table. Table 6-18 Modbus-TCP device parameter description Parameter Description Managed Object Device name Name Device IP address Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 227 Set this parameter to the authentication algorithm key Password configured on the subdevice. Value range: a–z, A–Z, 0–9, _ (8–15 characters, at least two types of characters, different from the user name or its reverse) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 228: Adding An Mts9604B-N20B1/Mts9606B-N20C2 Power Supply

    Step 2 On the main menu, choose Device Management > Configuration > Planning Configuration. Step 3 Choose the management domain where you want to create a device from the navigation tree on the left. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 229 Value range: a–z, A–Z, 0–9, _ (8–15 characters, at least two types of characters, different from the user name or its reverse) NOTE You are advised to set Authentication Password and Privacy Password to different values. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 230: Adding A Smartli

    This section describes how to create a SmartLi on the NetEco. Prerequisites ● You have the operation rights for Planning Configuration. ● You have created a management domain for the device to be added on the Planning Configuration page. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 231 NetEco and device. ● A non-SSL connection has security risks. You are advised to select the secure SSL connection. Timeout Period Timeout duration for a connection test. The default value is Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 232: Adding A Co Power Module

    Step 3 Choose the management domain where you want to create a device from the navigation tree on the left. Step 4 In the lower-left corner of the page, click the Device tab. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 233 Value range: a–z, A–Z, 0–9, _ (8–15 characters, at least two types of characters, different from the user name or its reverse) NOTE You are advised to set Authentication Password and Privacy Password to different values. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 234: Adding An Rpdu

    Subnet mask Enter the planned PDU2000 subnet mask. Gateway Enter the planned PDU2000 gateway. Address reporting the SNMP Enter the IP address of the NetEco the PDU2000 connects to. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 235: Creating An Rpdu On The Neteco

    It is recommended that the community be modified every three months. Write Community Set this parameter to the write community set on the device. Modifying community per three months is advised. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 236 You are advised to set Authentication Password and Privacy Password to different values. Step 8 Click on the toolbar to save the device information. Step 9 Click Connection test to start the connection test. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 237: Scenarios For Connecting The Ecc800-Pro Outside The Smart Module

    ● WAN ports support the Internet access and LAN ports support the intranet access. Connect the PC network port to the WAN1 port or LAN port on the ECC800-Pro based on the access network. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 238 Choose Tools > Internet options > Security, choose Add the ECC800-Pro IP address to the list of trusted sites. Figure 6-59 Adding an address Enable file download and set the security level of the trusted site to low. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 239 WebUI login page. Figure 6-61 WebUI login page On the login page, enter the preset user name admin and preset password Changeme, set the language, and click Log In. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 240: Setting The Ecc800-Pro Ip Address

    – After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 241: Setting The Ecc800-Pro System Type

    General. Procedure Step 1 Log in to the ECC800-Pro WebUI as an administrator. Step 2 Choose System > System Parameters > Site Configuration, set System type to General, and click Submit. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 242: Setting Rs485 Parameters For The Ecc800-Pro Collector

    Click Unhide All Advanced Signals. Click COM Port Parameters. Select a value from the Baud rate, Data bit, Stop bit, and Parity drop-down list boxes, and click Submit, as shown in Figure 6-64. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 243 Enable Security Authentication is set to Enable by default. If so, an authentication password must be set. If Enable Security Authentication is set to Disable, there is no need to set an authentication password but this is risky. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 244: Setting Neteco Parameters

    Set this parameter to Enable and System data click Submit. Settings > control System Paramete rs > Mobile Data. Step 3 Set NetEco communications parameters and authentication password on the ECC800-Pro WebUI. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 245: Creating An Ecc800-Pro Collector On The Neteco

    This section describes how to create an ECC800-Pro collector on the NetEco. Prerequisites ● You have created a smart module or container in Planning Configuration. ● The IP address of the NetEco connected has been configured on the ECC800- Pro WebUI. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 246 Step 5 Click Access in the Operation column. The Device Integration dialog box is displayed. Step 6 In the Device Integration dialog box, add the ECC800 to the specified management domain. Figure 6-66 Adding the ECC800-Pro by automatic discovery Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 247 ● The modification of the device name on the ECC800-Pro web client will be synchronized to the NetEco. Step 9 Click on the toolbar to save the device information. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 248: Setting The Transparent Transmission Function For The Ecc800-Pro Collector

    Step 3 In the Transparent Transmission of Local COM Ports area, set COM2(Port: 3212) to Enable and click Submit. NO TE Mapping relationship: COM1 corresponds to port 3211, COM2 port 3212, COM3 port 3213, and COM4 port 3214. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 249 Step 13 In the navigation tree on the left, choose Transparent Transmission Channel Management. Step 14 Click Modify after selecting the IP address of the ECC800-Pro connected to the NMS. Step 15 In the Modify dialog box, set Connection Mode. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 250: Setting Transparent Transmission For The Uim20A Expansion Module On The Ecc800-Pro Webui

    Step 4 Select UIM1 from the UIM drop-down list box, select Enable from the COM1Port drop-down list box, and click to Submit. Figure 6-68 Enabling transparent transmission for a UIM COM port Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 251 Integration. Step 14 In the navigation tree on the left, choose Transparent Transmission Channel Management. Step 15 Click Modify after selecting the IP address of the ECC800-Pro connected to the NMS. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 252: Adding Sensors

    DSS onsite. Procedure Step 1 Log in to the WebUI of the ECC800-Pro collector. Step 2 Choose Monitoring > System > ECC800 > Running Parameters > AI/DI_1 Port Settings. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 253: Setting Smoke Sensor And Water Leakage Sensor Parameters On The Ecc800-Pro Web

    Management > Device Addition > Auto Discover Device. Procedure Step 1 Log in to the WebUI of the ECC800-Pro collector. Step 2 Choose Monitoring > System > ECC800 > Running Parameters > AI/DI_1 Port Settings. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 254: Setting Device Monitoring Parameters Of An No/Nc Dry Contact On The Ecc800-Pro Web

    Step 1 Log in to the WebUI of the ECC800-Pro collector. Step 2 Choose Monitoring > System > ECC800 > Running Parameters > AI/DI_1 Port Settings. Step 3 Set AI/DI_1 to Enable. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 255: Creating An Icon For A Door Status Sensor On The Neteco

    The Toolbox dialog box is displayed. Step 5 Drag in the toolbox to the position where the door status sensor needs to be displayed in the view. The Property Panel dialog box is displayed. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 256 Center) 6 Adding Devices Figure 6-72 Property Panel Step 6 In the Basic Properties area, set basic properties. Table 6-34 Parameter configuration description Parameter Configuration Operation Name Enter a new name. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 257 1. Click the door status sensor icon and choose Close or Open under 2. In the displayed dialog box, click Yes. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 258 Step 7 In the Extended Properties area, set extended properties. Click Extended Properties to expand the area. Set extended properties based on the site requirements. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 259: Creating The Water Sensor On The Neteco

    Step 3 On the View page, double-click the equipment room where the water sensor is deployed. Step 4 Click on the toolbar on the left. The Toolbox dialog box is displayed. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 260 Configuration Operation Name Enter a new name. Counter 1. Click ... next to Counter. The Select Data dialog box is displayed. 2. Set Object and Counter to be added. 3. Click OK. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 261 Step 7 In the Extended Properties area, set extended properties. Click Extended Properties to expand the area. Set extended properties based on the site requirements. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 262: Modifying Alarm Names For Devices On The Neteco

    All the alarms of the device are displayed. Click in the Operation column of the alarm to be redefined. The Set Rule dialog box is displayed. Set New Name, New Severity, and New Type as required. Click OK. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 263: Modifying Performance Counter Names For Devices On The Neteco

    Step 3 In the navigation pane on the left, select a device. Step 4 Click the Sampling, Configuration, or Statistic tab and modify performance counter names. Step 5 Click Apply. ----End 6.5.2.2 Adding a Temperature and Humidity Sensor Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 264: Setting Monitoring Parameters For A T/H Sensor (Bom Number: 33010346)

    6.5.2.2.2 Creating a Temperature and Humidity Sensor on the NetEco Prerequisites ● You have the operation rights for Planning Configuration. ● You have created a management domain for the device to be added on the Planning Configuration page. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 265: Adding A Water Leakage Sensor

    Set this parameter to the address set on the device. Step 8 Click on the toolbar to save the device information. Step 9 Click Connection test to start the connection test. ----End 6.5.2.3 Adding a Water Leakage Sensor Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 266: Creating A Water Leakage Sensor On The Neteco

    For details about the ports on the ECC800-Pro collector, see 6.5.1.4 Setting RS485 Parameters for the ECC800-Pro Collector. Device Address Set this parameter to the address set on the device (set to 1 by default). Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 267: Adding A Hydrogen Sensor

    Table 6-38 Mapping between Hydrogen Sensor communications address and DIP switch Communicati ons Address BaudRate, DataBit, StopBit and Parity on hydrogen sensor cannot be set, the default setting is 9600, 8, 1 and None. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 268: Creating A Hydrogen Sensor On The Neteco

    Table 6-39 Modbus-RTU device parameter description Parameter Description Managed Object Device name Name Set this parameter to the IP address of the collector to which the device is connected. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 269: Adding The Access Management System

    6.5.3.2 Creating an Access Controller on the NetEco This section describes how to create an access controller on the NetEco. Prerequisites ● You have the operation rights for Access Control Management and Planning Configuration. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 270 Step 5 Click on the toolbar to save the device information. Step 6 On the Transmission Channel Management page, set the connection mode to secure mode and set the security password. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 271 Figure 6-80 Checking the access controller information NO TICE After the access controller is added, format it manually in the access controller list to avoid failure in initializing the access controller. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 272: Formatting An Access Controller On The Neteco

    Step 1 Set the baud rate of the NEWABEL CHD200G fingerprint controller to 9600 on the ECC800-Pro collector. The preset address is 1. The address does not need to be set. When creating the device on the NetEco, set Device Address to 1. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 273: Creating A Newabel Chd200G Fingerprint Controller On The Neteco

    Set this parameter to the port through which the device connects to the collector. For details about the ports on the ECC800-Pro collector, see 6.5.1.4 Setting RS485 Parameters for the ECC800-Pro Collector. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 274: Adding A Smart Cooling Product

    NetCol5000, and then modify the port parameters for the collector connecting to the NetCol5000 to ensure that the values of BaudRate, DataBit, StopBit, and Parity on the NetCol5000 are consistent with those for the collector port. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 275: Creating A Smart Cooling Product On The Neteco

    The ECC800-Pro connected to the device has been connected to the NetEco. ● Transparent transmission has been enabled for the COM port on the ECC800- Pro or UIM20A expansion module to which the device is connected. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 276: Adding A Chiller

    Step 9 Click Connection test to start the connection test. ----End 6.5.5 Adding a Chiller 6.5.5.1 Creating a Chiller on the NetEco This section describes how to create a chiller on the NetEco. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 277 Set this parameter to the address set on the device. Step 8 Click on the toolbar to save the device information. Step 9 Click Connection test to start the connection test. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 278: Adding A Ups

    NO TE For the UPS2000, the default values of BaudRate, DataBit, StopBit, and Parity are 9600, 8, 1, and None, respectively. If the parameters are changed, the actual parameter values prevail. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 279: Creating A Ups On The Neteco

    6.5.1.4 Setting RS485 Parameters for the ECC800-Pro Collector. Device Address Set this parameter to the address set on the device. Timeout Period Timeout duration for a connection test. The default value is Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 280: Adding A Pdu

    9600. Set BaudRate for the collector port to the same value. DataBit, StopBit, and Parity for the PDU8000 cannot be set on the WebUI. Their values are 8, 1, and None respectively. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 281: Creating A Pdu On The Neteco

    To delete a device, click the device and choose Delete under Step 7 Click the device. In the device parameter area on the right, set device parameters according to the following table. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 282: Adding A Fresh Air Unit

    Step 4 In the lower-left corner of the page, click the Device tab. Step 5 In the Device area, select Air Conditioner from the drop-down list box. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 283: Adding An Rpdu

    PDU2000 to ensure that the values of BaudRate, DataBit, StopBit, and Parity on it are consistent with those for the collector port. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 284: Creating An Rpdu On The Neteco

    Step 2 On the main menu, choose Device Management > Configuration > Planning Configuration. Step 3 Choose the management domain where you want to create a device from the navigation tree on the left. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 285 Timeout duration for a connection test. The default value is Step 8 Click on the toolbar to save the device information. Step 9 Click Connection test to start the connection test. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 286: Device Maintenance

    If the PSU is faulty, replace it. No abnormal noise is If abnormal noise is generated, generated. clean the fan. Cable The cable connection is Secure loose cables. connection secure. Cables are not damaged. Replace damaged cables. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 287: Routine Maintenance For The Uim20A Expansion Module

    UIM20A module is expansion faulty or the module is cables are not normal. properly connected. Check the cables or replace the UIM20A expansion module. 7.1.1.3 Routine Maintenance for VCN Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 288: Routine Maintenance For The Smoke Detector

    Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 289: Routine Maintenance For The Hydrogen Detection System

    AC the hydrogen input or replace the collector. power module by following instructions in the delivered documents. 2. If the fault persists, contact Huawei technical support. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 290: Routine Maintenance For The Region-Type Water Sensor And Water Detection Cable

    Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 291: Semi-Annual Maintenance

    NetEco Device Installation and Commissioning Guide (Data Center) 7 Device Maintenance 7.1.2 Semi-Annual Maintenance Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 292: Routine Maintenance For The Switch

    ● Steady red: The switch does not run properly after being registered, or alarms indicating that the power supply, fan, or temperature is abnormal are generated. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 293: Routine Maintenance For The Smart U Space Manager

    If so, reconnect environment environment the cable. If unit on the unit on the not, replace WebUI. WebUI. temperature sensor. 7.1.2.4 Routine maintenance for the temperature and humidity sensor Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 294: Routine Maintenance For The Camera

    For click the camera details about how to replace a name or icon camera. the left to view the real-time monitoring page. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 295: Routine Maintenance For The Access Control System

    Access controller Semi-annually Check If the access function whether access controller fails to controller operate properly, access works replace the controller properly. controller. works properly referring to the installatio n guide. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 296: Routine Maintenance For The Single-Door/Double-Door Magnetic Lock

    7.2.1.1 Replacing an ECC800-Pro Main Control Module Prerequisites NO TICE ● The ECC800-Pro main control module is hot-swappable. ● Before disconnecting cables from the ECC800-Pro main control module, label the cables based on the corresponding ports. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 297 Step 5 (Optional) Remove the SIM card from the corresponding slots of the ECC800-Pro main control module. Step 6 (Optional) Install the removed SIM card in the corresponding slot of the new ECC800-Pro main control module. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 298: Replacing An Ecc800-Pro Psu

    Step 2 Pull out the handle of the PSU to remove the PSU from the subrack. Step 3 Gently push the reserved PSU into the subrack along guide rails, and push the locking latch rightwards to secure the handle. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 299: Replacing Ecc800-Pro Antennas

    Step 2 Install the spare 4G antenna cables and RF_Z antenna cables in the original positions and connect them to the ECC800-Pro. ----End 7.2.1.4 Replacing a SIM Card and Micro SD Card Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 300 Step 4 Remove the SIM card and micro SD card from the card slot. Figure 7-6 Removing a SIM card and a micro SD card Step 5 Install the spare SIM card and micro SD card into the card slot. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 301: Replacing A Uim20A Expansion Module

    Step 2 Disconnect cables from the UIM20A expansion module. Step 3 Unscrew the mounting ears from the two sides of the UIM20A expansion module, and remove the UIM20A expansion module. Figure 7-8 Removing a UIM20A Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 302: Replacing A Smart U Space Manager

    Material: smart U space manager Figure 7-9 Smart U space manager installation diagram (main control box attached to the top of the cabinet interior) (1) Fastener (2) UIM20A Expansion Module (3) Main control box Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 303 Step 3 (Optional) If the main control box is faulty, perform the following steps to replace Label each cable based on the corresponding ports on the main control box. Remove the faulty main control box. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 304: Replacing Sensors

    ----End 7.2.4.2 Replacing the Hydrogen Detection System Prerequisites ● The hydrogen detection system needs to be replaced. ● A spare hydrogen detection system of the same model is available and functional. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 305 (2), fan cables to (3), and hydrogen sensor cables to (4). Step 6 Prepare one end of a network cable according to Table 7-18, and connect the cable to (7). Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 306 (7) RS485 Table 7-18 Pin mapping for the RS485 port Signal Function Pin 1 (orange-white) RS485+ Pin 2 (orange) RS485- Pin 3 (green-white) 12V+ 12+ input Pin 4 (blue) Pin 5 (blue-white) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 307: Replacing A Smoke Detector

    Step 3 Install a new smoke detector and reconnect the cables. Step 4 Install the new smoke detector to the base by rotating it in a direction opposite to Step Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 308: Replacing A T/H Sensor

    Prepare a water sensor or water detection cable of the same model. A water sensor consists of a water detection cable, water detector, and conversion cable. The water detection cable is laid out on the floor, connecting to the water Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 309 Remove the conversion cable at the conversion port for the water sensor and conversion cable. Connect a new water sensor to the conversion cable, as shown in Figure 7-15. Secure the new water sensor. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 310: Replacing A Location-Type Water Sensor And Water Detection Cable

    7.2.4.6 Replacing a Location-type Water Sensor and Water Detection Cable Prerequisites ● The water sensor needs to be replaced. ● A spare water sensor of the same model is available and functional. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 311: Replacing The Management System

    If an alarm is raised, the replacement is complete. 7.2.5 Replacing the Management System 7.2.5.1 Replacing an M2121 Camera Prerequisites ● A camera needs to be replaced. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 312: Replacing An Ivs1800

    An IVS1800 needs to be replaced. ● A spare IVS1800 of the same model is available and functional. Context NO TICE Videos cannot be recorded during the replacement of the IVS1800. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 313: Replacing A Hard Disk For The Ivs1800

    Step 6 Commissioning the IVS1800. If the video recording function works properly after commissioning, the IVS1800 is functional. ----End 7.2.5.3 Replacing a Hard Disk for the IVS1800 Prerequisites ● A hard disk needs to be replaced. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 314 Before the installation, ensure that the fastener of the hard disk tray is on a different side from the hard disk port, as shown in the lower left figure. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 315 P0–P3 to hard disks on the lower-layer hard disk tray and ports P4–P7 to hard disks on the upper-layer. Figure 7-23 Connecting data and power cables to hard disks Close the chassis cover, and use a PH2 screwdriver to fasten the rear screws. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 316: Replacing The Access Management System

    Step 4 Observe the hard disk indicator to check whether the hard disk works properly. ----End Follow-up Procedure If the hard disk works abnormally, contact Huawei technical support. 7.2.6 Replacing the Access Management System 7.2.6.1 Replacing an Access Controller Prerequisites ●...
  • Page 317 Step 5 Install the new access controller by performing the operations prior to Step 3 reverse order. Step 6 Reinstall the removed cables for the access controller according to the labels and start the access controller. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 318: Replacing A Double-Door Magnetic Lock

    Recommended tools and materials: crimping tool, Phillips screwdriver, hex key (delivered with the product package), step ladder (2 m). Procedure Step 1 Remove the cover of the magnetic lock, as shown in Figure 7-27. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 319 Step 2 Remove magnetic lock cables from the terminals and route the cables out of the cable holes, as shown in Figure 7-28. Figure 7-28 Removing cables Step 3 Remove the base and the magnetic lock, as shown in Figure 7-29. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 320 Remove the fixing plate from the magnetic lock using the delivered hex key as shown in Figure 7-31. NO TE The four hex socket screws should be removed in this step. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 321 If gaps exist between the electromagnets and the magnetic iron plates, rectify the fault by referring to Figure 7-32. If the magnetic iron plates are not level with each other, adjust them by using the spacer shown in Figure 7-33. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 322: Replacing A Single-Door Magnetic Lock

    Spare card readers of the same model are available and functional. Context Prepare a spare access card reader of the same model. Recommended tools and materials: crimping tool and Phillips screwdriver Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 323 Step 2 Remove the mounting plate of the card reader, as shown in Figure 7-34. Figure 7-34 Removing the mounting plate Step 3 Remove the screws on the card reader cover and remove the cover, as shown in Figure 7-35. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 324 Figure 7-36 Removing the card reader Step 5 Take out a new card reader. Step 6 Remove the screws that secure the card reader and take out the card reader cover, as shown in Figure 7-37. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 325: Replacing A Fingerprint And Card Reader

    Prerequisites ● Recommended tool: Phillips screwdriver ● A fingerprint and card reader needs to be replaced. ● A spare fingerprint and card reader of the same model is available and functional. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 326 Step 5 Secure the fingerprint and card reader to the bottom plate. Step 6 Choose System > Service Settings > Data Center Planning from the main menu. The Data Center Planning page is displayed. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 327: Replacing A Card Reader With A Keypad

    Step 1 Remove the screw that secures the card reader with a keypad, and remove the cable, as shown by (1), (2), and (3) in Figure 7-41. Figure 7-41 Removing a bottom plate Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 328: Replacing A Fingerprint And Card Reader With A Keypad

    Figure 7-42 Fingerprint and card reader with a keypad Procedure Step 1 Remove the screw that secures the fingerprint and card reader with a keypad, and remove the cable, as shown by (1), (2), and (3) in Figure 7-43. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 329: Replacing An Emergency Door Release Button

    An emergency door release button needs to be replaced. ● A spare emergency door release button of the same model is available and functional. Context Figure 7-44 Emergency door release button Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 330 Step 4 Remove the cover of the emergency door release button using a Phillips screwdriver and remove the glass. If the room door can be opened normally, the emergency door release button is functional. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 331 NetEco Device Installation and Commissioning Guide (Data Center) 7 Device Maintenance Step 5 Install the emergency door release button. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 332: Faq

    Step 3 Check whether the angle and tightness of the door magnet are appropriate. ● If the angle and tightness are inappropriate, adjust them. ● If the angle and tightness are appropriate, contact Huawei technical support. ----End 8.2 How Do I Change the NetEco IP Address? Prerequisites You have the operation rights of the ECC800-Pro WebUI and UPS2000–G.
  • Page 333 In the SNMP Trap area, if Trap Target Address is the same as the NetEco IP address before the modification, select this row and click Delete. In the SNMP Trap area, click Add. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 334: Logging In To The Neteco App

    8.3 Logging In to the NetEco App Logging In to the App Step 1 Press and hold down the UPS power button for 0.5s to enable the WiFi of the UPS. (The WiFi indicator will turn on.) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 335 Step 3 Tap UPS. The Connect WLAN screen is displayed. Use either of the following methods to connect to the WLAN network. Figure 8-4 Connect WLAN ● Manually connect to WLAN Enable WLAN on the mobile device. (Skip this step if WLAN has been enabled.) Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 336 Step 6 After successful login, the Quick Settings screen is displayed. Verify parameters such as the voltage level, frequency, and battery settings based on the actual situation. You can manually set parameters as required. Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 337 Center) 8 FAQ Figure 8-6 Quick Settings NO TE If it is not the first login, skip the quick settings operation. Step 7 Tap OK. The home screen is displayed. ----End Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 338: Acronyms And Abbreviations

    Data Encryption Standard digital input digital output energy control center Ethernet fast Ethernet iBAT iBattery integrated circuit iCooling iCooling IEEE Institute of Electrical and Electronics Engineers Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 339 Ethernet radio frequency Revist-Shamir-Adleman Algorithm secure digital SFTP Secure File Transfer Protocol SecureHashAlgorithm subscriber identity module short message service SNMP Simple Network Management Protocol Secure Sockets Layer Transport Layer Security Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.
  • Page 340 NetEco Device Installation and Commissioning Guide (Data Center) 9 Acronyms and Abbreviations uninterruptible power system universal serial bus video cloud node WiFi wireless fidelity Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd.

Table of Contents