Scenarios For Connecting The Ecc800-Pro Outside The Smart Module; Preparing A Monitoring Cable - Huawei iMaster NetEco V600R021C10 Device Installation And Commissioning Manual

Table of Contents

Advertisement

iMaster NetEco
Device Installation and Commissioning Guide (Data
Center)
4.3 Scenarios for Connecting the ECC800-Pro Outside
the Smart Module

4.3.1 Preparing a Monitoring Cable

Prerequisites
Preparing a Cord End Terminal
Figure 4-19
Figure 4-19 Preparing a cord end terminal
Preparing the RS485 Monitoring Cable
Figure 4-20
collector.
Issue 02 (2021-05-12)
A twisted pair, cord end terminal, and RJ45 connector are prepared.
The following tools are prepared:
Wire stripper
Crimping tool
RJ11 crimping tool
Electrician's knife
Polyvinyl chloride (PVC) insulation tape
shows how to prepare a cord end terminal.
shows how to prepare a cord end terminal for the ECC800-Pro