Huawei iMaster NetEco V600R021C10 Device Installation And Commissioning Manual page 134

Table of Contents

Advertisement

iMaster NetEco
Device Installation and Commissioning Guide (Data
Center)
Figure 4-43 NetCol5000-A020/NetCol5000-C030 communications port J73
(1) J73 (teamwork bus port and host monitoring port)
● The main control board can be Arm7 or M4. The appearance varies with the
model delivered.
● The Arm7 main control board has S1 and S2 DIP switches, and the M4 main
control board has only the S2 DIP switch. The S1 DIP switch needs to be set for
the Arm7 main control board and does not need to be set for the M4 main
control board.
● The Arm7 main control board uses the software of V100R001, and the M4
main control board uses the software of V100R002.
● You need to set only the seventh toggle switch based on teamwork
requirements and leave other toggle switches in their default status.
Figure 4-44 NetCol5000 main control board
(1) Teamwork communications port 1
(3) S1 DIP switch of the main control board
Table 4-43 Operations of the DIP switch
Toggle
Switch
1
Issue 02 (2021-05-12)
NO TICE
Default Value
OFF
Copyright © Huawei Technologies Co., Ltd.
4 Connecting Monitoring Cables to Devices
(2) Teamwork communications port 2
(4) S2 DIP switch of the main control board
Operations
Remaining in OFF
123

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents