Checking The Installation Of Components In The Cabinet; Checking The Installation Of Power Cables And Ground Cables - Huawei iMaster NetEco V600R021C10 Device Installation And Commissioning Manual

Table of Contents

Advertisement

iMaster NetEco
Device Installation and Commissioning Guide (Data
Center)
SN
9
10
11
12
13
5.2 Checking the Installation of Components in the
Cabinet
SN
1
2
3
4
5
6
7
8
9
5.3 Checking the Installation of Power Cables and
Ground Cables
Issue 02 (2021-05-12)
Check Item
All the outlets or inlets of the cabinets are sealed. The gap around a
cover plate does not exceed the width of the cover plate. If a bag is used,
the opening of the bag is tied up. The sizes of the outlets that use
plastics are appropriate. You can use other appropriate, insulated, or
flame-resistant materials to seal the outlets.
There are excessive hair bands, lines, and other wastes.
All the configured filler panels are installed.
The ESD wrist strap is inserted into the ESD installation hole.
The cabinet labels are smooth and tidy.
Check Item
The devices are installed in the correct positions as designed.
All the panel screws of the devices are installed and secure.
The panel and exterior of each device are not dirty, and the paint is not
scraped off.
The labels (coating of the subrack, plate nameplate, transport label, and
product nameplate) of each device are not peeled off.
The bar code of each device is not peeled off.
The ejector lever of each board is placed in position.
The captive screws of each board are secure.
There is no vacant slot in the subrack, and filler panels are installed in
vacant slots.
A protective cover is installed for the power module if the power module
is configured with a protective cover.
Copyright © Huawei Technologies Co., Ltd.
5 Checking the Installation
135