Step 1 Fold the delivered cutout template along the dotted line by 90 degrees, as shown
by (2) in
Step 2 Close the door, place the cutout template near the top of the door frame in the
door opening direction, mark the mounting holes, and drill holes, as shown in
Figure
Figure 3-67 Mark the installation position
(1) Door frame
Step 3 Remove the hoisting strip using the delivered hex key.
Figure 3-68 Removing a hoisting strip
Issue 02 (2021-05-12)
Check that the room door is a single-door that can be rotated open outwards.
The door frame should be over 42 mm thick. A glass door is not supported.
The cable routes are planned.
Figure
3-67.
3-67.
NO TE
Two hex socket screws need to be removed in this step.
Copyright © Huawei Technologies Co., Ltd.
(2) Cutout template
3 Installing Devices
(3) Door panel