Huawei iMaster NetEco V600R021C10 Device Installation And Commissioning Manual page 67

Table of Contents

Advertisement

iMaster NetEco
Device Installation and Commissioning Guide (Data
Center)
Figure 3-63 Removing a hoisting strip
Step 4 Secure the hosting strip using the delivered screws, as shown by (1) in
3-64.
Pay attention to the direction of the hoisting strip, and ensure that the bulging
surface of the magnetic lock faces the magnet.
Figure 3-64 Installing a magnetic lock
Step 5 Route the electronic lock cable through the cable hole, and secure the electronic
lock using a hex key, as shown by (2) in
Step 6 Install the magnet.
1.
Issue 02 (2021-05-12)
NO TICE
Take out the magnet, and knock the positing pins of the magnet into the
magnet using a rubber mallet.
Copyright © Huawei Technologies Co., Ltd.
Figure
3-64.
3 Installing Devices
Figure
56