ABB REG650 Technical Manual page 158

Generator protection
Hide thumbs Also See for REG650:
Table of Contents

Advertisement

Section 7
Impedance protection
152
1.5
The 2nd
1
pole slip
occurred
0.5
Zone 2
Zone 1
0
limit of reach ®
lens determined ®
-0.5
by the setting
Pickup Angle = 120°
-1
-1.5
-1
ANSI10000109 V1 EN
Figure 68:
Loci of the complex impedance Z(R, X) for a typical case of generator
losing step after a short circuit that was not cleared fast enough
Under typical, normal load conditions, when the protected generator supplies the active
and the reactive power to the power system, the complex impedance Z(R, X) is in the
1st quadrant, point 0 in
Figure
conditions, the centre of oscillation is at the point of fault, point 1, which is logical, as
all three voltages are zero or near zero at that point. Under the fault conditions the
generator accelerated and when the fault has finally been cleared, the complex
impedance Z(R, X) jumped to the point 2. By that time, the generator has already lost
its step, Z(R, X) continues it way from the right-hand side to the left-hand side, and the
1st pole-slip cannot be avoided. If the generator is not immediately disconnected, it
then continues pole-slipping see
are shown. Under out-of-step conditions, the centre of oscillation is where the locus of
the complex impedance Z(R, X) crosses the (impedance) line connecting the points SE
(Sending End), and RE (Receiving End). The point on the SE – RE line where the
trajectory of Z(R, X) crosses the impedance line can change with time and is mainly a
function of the internal induced voltages at both ends of the equivalent two-machine
system, that is, at points SE and RE.
Measurement of the magnitude, direction and rate-of-change of load impedance
relative to a generator's terminals provides a convenient and generally reliable means
of detecting whether machines are out-of-phase and pole-slipping is taking place.
Measurement of the rotor (power) angle is important as well.
¬
X in Ohms
The 1st
pole slip
occurred
RE
- -
- -
- -
- -
- -
- - - -
- - - -
- -
- - - -
- - - -
- -
- -
- - - -
- - - -
- -
3
- - - -
1
-
- - -
2
-
- - -
-
- - -
-
- - -
-
- - -
-
-
- - -
- - -
^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^
-
-
- - -
^ ^ ^ ^ ^ ^
- - -
-
-
- - -
- - -
-
-
-
-
- - -
- - -
-
-
- - -
- - -
relay
-
-
- - -
- - -
-
-
- - -
- - -
-
-
- - -
- - -
-
-
- - -
- - - -
-
- -
- - - -
- -
- - - -
- -
- - - -
- - - - -
- -
0 ®
pre-disturbance Z(R, X)
- - - - -
- -
- -
- -
- -
- -
1 ®
Z(R, X) under 3-phase fault
SE
2 ®
Z(R, X) when fault cleared
3 ®
Z when pole-slip declared
-0.5
0
0.5
Real part (R) of Z in Ohms
68. One can see that under a three-phase fault
Figure
68, where two pole-slips (two pole-slip cycles)
1MRK 502 043-UUS B
trajectory
of Z(R, X)
to the 3rd
pole-slip
Pre-disturbance
normal load
Z(R, X)
0
R in Ohms
1
1.5
ANSI10000109-1-en.vsd
Technical Manual

Advertisement

Table of Contents
loading

Table of Contents