Step 7. Press
Step 8. If an isolation calibration must be performed using a LOAD standard, follow the procedure
below.
a. Connect a LOAD standard to the test port (connector to which the DUT will be
connected) selected in Step 5.
Figure 4-5
Connecting the Load Standard
b. Press
Step 9. Press
process. Upon pressing the key, calibration coefficients will be calculated and saved. The
error correction function will also be automatically enabled.
NOTE
By pressing
calibration coefficients. To cancel the calibration without saving the new calibration
coefficients, press
Chapter 4
OPEN/SHORT Response Calibration (Reflection Test)
or
to start the calibration measurement.
Open
Short
to start the measurement on the LOAD standard.
Load (Optional)
to terminate the response calibration (and the LOAD isolation calibration)
Done
, previously saved calibration coefficients will be overwritten with new
Done
successively.
Cancel - OK