Hardware Installation Guidelines
8.
Wire routing note: UL two panel installation instructions for LNL-CTX enclosures
To install multiple Lenel hardware panels into a single enclosure, the following guidelines must be used
for certified UL installations.
All wire connections that cross over the hinge side of the door must be wire wrapped or tie wrapped
together.
All wire must be routed behind the hardware panel so that the wires are secure from movement
when opening and closing the door.
All connections for the lock side of the enclosure must come from behind the Lenel hardware
devices.
2.2.2
LNL-AL600ULX-4CB6 Installation
The LNL-AL600ULX-4CB6 should be installed in accordance with article 760 of the National Electrical
Code of NFPA70 as we as all applicable local codes. If you are located in Canada, refer to the Canadian
Electrical Code.
1.
Mount the enclosure in desired location.
2.
The power supply is pre-wired to the ground (chassis). Connect main incoming ground to the provided
green grounding conductor lead. Connect unswitched AC circuit (115 VAC/60 Hz) dedicated to the
Burglar Alarm/Access Control Subsystem to terminals marked L, G, N.
LNL-AL600ULX-4CB6
Enclosure Dimensions:
24"H x 18"W x 4.5"D
Unit includes Cabinet,
Cabinet Tamper Switch,
Power Supply, Power
Distribution Circuit, Battery
Leads, Lenel access
hardware mounts/screws,
and Lock.
Power
Limited
Devices
3.
Keep power limited wiring separate from non-power limited wiring (115 VAC/60 Hz Input, Battery
wires). Minimum 0.25 inch spacing must be provided between power wires.
4.
Connect devices to be powered to terminals marked (1P-1N, 2P-2N, 3P-3N, 4P-4N) and distribute
evenly. Each output is rated at 1.5 amps max.
34 —
revision 7
LENEL Hardware
LENEL Hardware
Input 115 VAC, 60Hz, 1.9 amp.
CAUTION:
De-energize
unit prior to
servicing. So
not expose to
rain or
moisture.
LENEL Hardware
LENEL Hardware
1P, 2P, 3P, and 4P = Fused Outputs
1N, 2N, 3N, and 4N = Common Outputs
Hot - Black
Neutral - White
Ground - Green
black
green
white
Battery & AC
Supervision
Circuit
(power limited)
+ BAT --
+ DC --
Main Fuse
ON - OFF
PD4A
Input
To Battery
F1
in LNL-CTX
F2
F3
F4
Output Circuit 1
Output Circuit 2
Output Circuit 3
Output Circuit 4