Verifying the installation

Once you have finished installing your RLC and connecting the cables, verify
that you have completed these procedures properly according to the indications
discussed below.

Indications of proper installation

An RLC automatically performs a self-test when inserted into its card slot. A
successful self-test indicates proper installation. The Maintenance LED
confirms a successful self-test by:
blinking three times
turning off (when enabled by the switch)
remaining off (if enabled by the switch)
Note: Refer to "LED indicators" on page 8 for a further explanation of LED
indicator behavior at startup.

Indications of proper cable connections

The ability to successfully log on to the RLC using Configuration Manager
software indicates proper cable connections at the RLC. To perform this task,
install the software first (refer to page 90). Once this task is completed, continue
with "Starting Configuration Manager" on page 93.
Confirm the cable connections before attempting the troubleshooting
procedures.
Note: If the RLC cables are properly connected and you still cannot log on, refer
to Chapter 8, "Troubleshooting".