How to Install a T1000 AS Frame
8.
Replace tiles if necessary.
9.
This procedure is complete.
Next, go to Procedure 4-8 on page 4-18.
How to Anchor on Raised Floor Using Support Channel with Spring Nut
Use the following procedure to anchor the HD frame to the raised floor tiles using
the a support channel with spring nut.
Procedure 4-7.
1.
Ensure that Procedure 4-3, "Create Cable and Anchor Holes for Raised
Floors," on page 4-5 has already been performed.
2.
Insert threaded rods through the frame and the raised floor and into the
spring nut in the support channel as shown in see Figure 4-8.

Figure 4-8. Anchor Assembly for Support Channel with Spring Nut

Note: When an anchor assembly is used on a raised floor, the anchor
assembly must be disassembled and the correct length of threaded rod of the
proper diameter must be used for the floor height requirement. Finger tighten
any nuts above raised floor before tightening nuts below raised floor
Large washer
Fiber washer
Nylon shoulder
washer
Threaded rod
(see note)
4-16
Anchor Frame with Support Channel/Spring Nut
Anchor
Raised Floor
Small steel
washer
Support channel
(example Unistrut)
Torque nut
(red plastic cover)
Frame floor
Isolator pad
Raised floor
Raised floor
Concrete floor
Spring nut
910-0095-001 Revision J November 2007
Frame floor
04_anchor_rsdflr_no_cone