Figure 4-5. Anchoring On Raised Floor Over Concrete Slab - Tekelec T1000 Hardware Manual

Tekelec 1000 application server hardware manual
Table of Contents

Advertisement

How to Install a T1000 AS Frame
7.
Insert each threaded rod/anchor assembly into its hole, with the cone nut at
the bottom, and tighten with a 3/4 inch (19mm) wrench until the top nut of
the torque nut breaks free (this nut is called the twist-off nut in Figure 4-4 on
page 4-10).

Figure 4-5. Anchoring on Raised Floor Over Concrete Slab

Large washer
Small washer
Nut
8.
At the top end of each threaded rod, thread on a 5/8 inch nut until it is below
the level where the floor tile will meet the threaded rod.
9.
On top of the 5/8 inch nut, drop a small steel washer and then a large steel
washer.
10.
Return tiles to their original positions, fitting the anchor holes in the tiles over
the threaded rod assemblies.
11.
Lay the isolator pad on the raised floor with the holes in the isolator pad
aligned over the threaded rod assemblies.
12.
Roll the frame (still on the dolly) into position above the isolator pad.
13.
Lower the frame onto the floor with the holes in the frame aligned over the
threaded rod assemblies. For instructions about how to lower the frame, refer
to 822-0094-02.
4-12
Frame
Finger tighten nuts above
raised floor before tightening
nuts below raised floor
Flat washers
and nuts
side
Locking nut
Washers
Holddown plate
Isolator pad
Raised floor
Concrete floor
Anchor assembly
with threaded rod
910-0095-001 Revision J November 2007