Figure 18-32     Installing the XBU
9.
Connect the crossbar cables.
Connect the crossbar cables to the XBU. For details, see
Crossbar
Caution - When connecting the crossbar cable, do not hold the pull-tab but hold the
connector part to insert it into the port for the connection, and push in the connector
part. If you hold the pull-tab when connecting the crossbar cable, it may become
impossible to remove the cable from the XBU.
Caution - A loose crossbar cable connection may, on rare occasions, cause an error
due to poor connection. After connecting a crossbar cable, push it in again so that it is
tightly in place to prevent any improper connection. Do not hold only the cable when
performing the work at this time. Otherwise, the cable may bend out of shape. For
details, see step 4 in
Note - The destination port for the XBU is described on a label affixed to the crossbar cable.
Check the label first and connect the cable to the port of the XBU. For crossbar cable
connection destinations, see "4.3 Connecting Crossbar Cables" in the Fujitsu SPARC
M12-2S Installation Guide.
10. Install the PCICS.
Install the PCICS in the server, and then secure the PCICS. For details, see
484
Fujitsu SPARC M12-2/M12-2S Service Manual ・ January 2023
Cable."
"19.4 Installing the Crossbar
Installing a PCIe
Card."
"19.4 Installing the
Cable."
"12.4